Project Details Project Details

Project Name
Capital Dredging (Kochi) Project
Project Brief
Capital dredging of the approach channel and ICTT berth basin at Kochi
Sector
Transport
Sub-Sector
Ports (excluding captive)
Project Capacity
Not Available
Location The geographical location of the project
Kerala
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Not Available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Cochin Port Trust
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Not Available
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
Not Available
Date Of Project Completion(Actual)
Not Available
Date Of Project Completion(as per Contract)
Not Available
Project Cost
Project Cost (as per Contract) in Rs Crore
33.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
Not Available
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Available