Project Details Project Details

Project Name
Setting up a 1,200 MW coal based power plant Phase I (Unit 1 & 2) at Raghunathpur#
Project Brief
The project involved setting up a 2x600 MW coal based power plant - Phase I (Unit 1 & 2) at Raghunathpur in Purulia district.
Sector
Energy
Sub-Sector
Electricity generation (grid)
Project Capacity
1200.0 MW (Mega Watt)
Location The geographical location of the project
West Bengal
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Completion delayed due to land constraint & shortage of water. Unit I got completed in April 2014.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Damodar Valley Corporation
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Reliance Infrastructure Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
14-Dec-2007
Date Of Project Completion(Actual)
31-Mar-2016
Date Of Project Completion(as per Contract)
14-Feb-2011
Project Cost
Project Cost (as per Contract) in Rs Crore
6,744.99
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
8,781.30
Project Cost(Actual) in Rs Crore Actual cost of the project
8,781.30
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.