Project Details Project Details

Project Name
Laying of Jiribam-Impal BG railway line in length of 97.9 km
Project Brief
The project involves construction of new BG railway line from Jiribam to Impal in Manipur.
Sector
Transport
Sub-Sector
Railway track, tunnel, viaducts, bridges
Project Capacity
110.62 KM (Kilometer)
Location The geographical location of the project
Manipur
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
Not Available

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
Northeast Frontier Railway
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Hindustan Construction Company Limited-Coastal Project Private Limited (JV)
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
Not Available
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
31-Mar-2018
Project Cost
Project Cost (as per Contract) in Rs Crore
5,996.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
13,809.00
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable