Project Details Project Details

Project Name
Setting up of 520 MW Tapovan Vishnugad hydel power unit at Chamoli
Project Brief
The project involves setting up of 4x130 MW hydel power plant across the River Dhauliganga in Chamoli.
Sector
Energy
Sub-Sector
Renewable energy (grid)
Project Capacity
520.0 MW (Mega Watt)
Location The geographical location of the project
Uttarakhand
Project Status
Completed
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
The project was delayed due to delay in procurement of tunnel boring machine by civil contractor, flash flood in June 2013 . (Source: Chief Engineer - Co-ordination , CEA)

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
NTPC Limited
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Larsen & Toubro Limited
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
30-Nov-2006
Date Of Project Completion(Actual)
Not Available
Date Of Project Completion(as per Contract)
31-Mar-2013
Project Cost
Project Cost (as per Contract) in Rs Crore
2,978.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
3,846.30
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Available
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.