Project Details Project Details

Project Name
Setting up of 600 MW Kameng hydel power unit at West Kameng#
Project Brief
The project involves setting up of 4x150 MW Kameng hydel power unit in West Kameng.
Sector
Energy
Sub-Sector
Renewable energy (grid)
Project Capacity
600.0 MW (Mega Watt)
Location The geographical location of the project
Arunachal Pradesh
Project Status
Under Construction
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector.
Government
Any Other Information Any other relevant information for the project
The project was delayed due to change in Crest level from EL 755m to 735m, length of dam increased from 247.3m to 264.15m, diversion arrangement modified.

Name Of Authority Name of the government agency that is the implementing authority for the project
Name Of Authority
North Eastern Electric Power Corporation Limited
Project Contractor Name of the concessionaire executing the project along with contact details such as name of the person, address, email, phone, fax, etc.
Name Of Contractor
Patel Engineering Limited-Unity Infra (JV)
Project Timelines
Date Of Award Of Project The date on which the work order/notice to proceed was issued by the project authority to the developer
08-Apr-2004
Date Of Project Completion(Actual)
Not Applicable
Date Of Project Completion(as per Contract)
31-Dec-2009
Project Cost
Project Cost (as per Contract) in Rs Crore
4,654.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per original estimates
6,179.96
Project Cost(Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.