Project Details Project Details

Project Name
Delhi-Meerut Expressway and other connecting roads including 6/8 laning of NH24, NH58,NH235 on DBFOT(Toll) basis*
Project Brief
Delhi-Meerut Expressway and other connecting roads including 6/8 laning of NH-24 from km 0.000 to km 49.23, NH-58 from km 6.800 to km52.528 and  NH-235 from km 0.360 to km 8.800 on DBFOT  (Toll) basis in the State of Delhi and Uttar Pradesh
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
150.147 KM (Kilometer)
Location The geographical location of the project
Multi State/ Centre
Type of PPP Variant of PPP model adopted for implementation of the project
Design-Build-Finance-Operate-Transfer (DBFOT)
Project Status
Under Construction
Concession Duration (In Months)
Not Available
Bid Parameter Criteria adopted for award of project
Not Available
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
This is a PPPAC Recommended Project. Updated status for the project is not available.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Ministry of Road Transport and Highways
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
Not Available
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
Not Available
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
30-Dec-2015
Construction Completion Date (as per Concession Agreement)
Not Available
Date to Start of Commercial Operation (as per Concession Agreement)
Not Available
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Applicable
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
Not Available
Concession End Date (Actual) Actual end date of the concession
Not Applicable
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
6,571.01
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
10,000.00
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.