Project Details Project Details

Project Name
Electricity Distribution New Delhi city (BRPL)
Project Brief
BSES Rajdhani Power Limited (hereinafter referred to as “the Petitioner/BRPL”),acompanyincorporatedundertheCompaniesAct,1956, and having its registered office at BSES Bhawan, Nehru Place, New Delhi –110019, is a license holder for carrying on the business of Distribution and etail Supply of electrical energy within the Area of Supply as specified in the “License for Distribution and Retail Supply of Electricity” issued by the Hon’ble Commission. The Petitioner came in existence in 1 July, 2002 post the unbundling of the erstwhile Delhi Vidyut Board (DVB). It is a joint venture between Reliance Infrastructure Limited and Government of National Capital Territory of Delhi (here in after referred to as “Go NCTD”
Sector
Energy
Sub-Sector
Electricity Distribution
Project Capacity
Not Available
Location The geographical location of the project
Delhi (UT)
Type of PPP Variant of PPP model adopted for implementation of the project
Licensee Model
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
Not Available
Bid Parameter Criteria adopted for award of project
Not Available
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
The mentioned project cost is the approved Gross Fixed Assets value (total investment) of the private companies as submitted to the State Elecricity Regulatory Commission in the tariff orders/annual reports.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
BSES RajdhaniPowerLimited (BRPL)
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
BSES Rajdhani Power Ltd. (BRPL), New Delhi
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
Not Available
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
Not Available
Construction Completion Date (as per Concession Agreement)
Not Available
Construction Completion Date (Actual) Actual Construction completion date
31-Mar-2017
Date to Start of Commercial Operation (as per Concession Agreement)
Not Available
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Available
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
Not Available
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Available
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
Not Available
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
6,021.00