Project Details Project Details

Project Name
Jaipur City ring road project phase I*
Project Brief
Development of ring road around Jaipur city (Southern Corridor - Agra road -Tonk road - Phaggi road - Ajmer road) phase-I
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
47.0 KM (Kilometer)
Location The geographical location of the project
Rajasthan
Type of PPP Variant of PPP model adopted for implementation of the project
Design-Build-Finance-Operate-Transfer (DBFOT) Toll
Project Status
Under Construction
Concession Duration (In Months)
Not Available
Bid Parameter Criteria adopted for award of project
Not Available
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
Now the project is implemented by NHAI, MoU signed with NHAI on 11-Aug-2017, Data captured from planning portal government of Rajasthan, 15-11-2018. Updated status for the project is not available.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Jaipur development Authority
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
M/s Gowar Construction Company Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
Not Available
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
16-May-2011
Construction Completion Date (as per Concession Agreement)
31-Oct-2017
Date to Start of Commercial Operation (as per Concession Agreement)
31-Oct-2017
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Applicable
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
Not Available
Concession End Date (Actual) Actual end date of the concession
Not Applicable
Project Grant
Type Of Grant
Not Available
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
890.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.