Project Details Project Details

Project Name
Jamb Wind Power Project, Satara district
Project Brief
Development of wind power project of 28 MW capacity at Jamb, Satara district, Maharashtra
Sector
Energy
Sub-Sector
Renewable energy (grid)
Project Capacity
28.0 MW (Mega Watt)
Location The geographical location of the project
Maharashtra
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Own-Operate (BOO)
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
Not Available
Bid Parameter Criteria adopted for award of project
Not Available
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
Financial Closure Date captured from PPIAF, rest of the information captured from VERRA Project Database website and Renew Power website, 14-11-2018

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Not Available
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
Renewable Energy Private Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
Not Available
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
31-Mar-2013
Appointed Date
Not Available
Construction Completion Date (as per Concession Agreement)
Not Available
Construction Completion Date (Actual) Actual Construction completion date
Not Available
Date to Start of Commercial Operation (as per Concession Agreement)
Not Available
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Available
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
Not Available
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Available
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
Not Available
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
165.90
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.