Project Details Project Details

Project Name
Implementation of 76 MLD sewage treatment plant at Kasba Bawda in Kolhapur
Project Brief
The project involved implementation of sewage treatment plant to control pollution of Panchganga river at Kasba Bawda in Kolhapur district under National River Conservation Project.
Sector
Water Sanitation
Sub-Sector
Sewage collection, treatment and disposal system
Project Capacity
76.0 MLD (Millons Liter per day)
Location The geographical location of the project
Maharashtra
Type of PPP Variant of PPP model adopted for implementation of the project
Design-Build-Finance-Operate-Transfer (DBFOT)
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
180
Bid Parameter Criteria adopted for award of project
Highest premium
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
Not Available

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Kolhapur Municipal Corporation
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
Vishwa Infrastructure & Services Private Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
04-Nov-2010
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
Not Available
Construction Completion Date (as per Concession Agreement)
03-Nov-2012
Construction Completion Date (Actual) Actual Construction completion date
14-Nov-2014
Date to Start of Commercial Operation (as per Concession Agreement)
03-Nov-2012
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
14-Nov-2014
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
03-Nov-2025
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Available
Grant Amount in Rs Crore
39.90
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
57.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
57.00
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.