Project Details Project Details

Project Name
Operation & maintenance of Kolaghat-Haldia section of NH-41
Project Brief
The project involved operation & maintenance of Kolaghat-Haldia section of NH-41 of 53 km.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
53.0 KM (Kilometer)
Location The geographical location of the project
West Bengal
Type of PPP Variant of PPP model adopted for implementation of the project
Management Contract (O&M)
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
108
Bid Parameter Criteria adopted for award of project
Revenue Share
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
Data is logically checked and corrected.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
National Highways Authority of India (NHAI)
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
Dineshchandra R Agarwal Infracon Private Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
29-May-2008
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
01-Sep-2008
Construction Completion Date (as per Concession Agreement)
01-Sep-2010
Construction Completion Date (Actual) Actual Construction completion date
01-Mar-2013
Date to Start of Commercial Operation (as per Concession Agreement)
01-Sep-2010
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
01-Mar-2013
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
31-Aug-2017
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
522.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
622.00
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.