Project Details Project Details

Project Name
Implementation of solid waste management unit in Fatehpur district
Project Brief
The project involved implementation of solid waste management unit in Fatehpur district. The scope of work includes door to door collection processing disposal.
Sector
Water Sanitation
Sub-Sector
Solid waste management
Project Capacity
55.0 TPD (Tonne per day)
Location The geographical location of the project
Uttar Pradesh
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Own-Operate-Transfer (BOOT)
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
360
Bid Parameter Criteria adopted for award of project
Tariff or User charge
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
Not Available

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Uttar Pradesh Jal Nigam
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
A2Z Green Waste Management Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
18-Jan-2011
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
Not Available
Construction Completion Date (as per Concession Agreement)
Not Available
Construction Completion Date (Actual) Actual Construction completion date
31-Jul-2013
Date to Start of Commercial Operation (as per Concession Agreement)
Not Available
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
31-Jul-2013
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
Not Available
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Construction Grant
Grant Amount in Rs Crore
9.38
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
14.29
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
14.29
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.