Project Name
Setting up of 8.0 MW Upper Joiner (Stage II) hydel power unit in Chamba
Project Brief
The project involves setting up of Upper Joiner (Stage II) hydel power unit in Chamba district.
Sector
Energy
Sub-Sector
Renewable energy (grid)
Project Capacity
8.0 MW (Mega Watt)
Location The geographical location of the project
Himachal Pradesh
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Own-Operate-Manage (BOOM)
Project Status
Under Construction
Concession Duration (In Months)
480
Bid Parameter Criteria adopted for award of project
Others
Other Bid Parameter Other bid parameter name
MoU route with fixed royalty
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
Not Available

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Directorate of Energy, Himachal Pradesh
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
Chamba Hydel Power Projects Private Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
15-Jun-2002
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
16-Mar-2012
Construction Completion Date (as per Concession Agreement)
31-Dec-2018
Date to Start of Commercial Operation (as per Concession Agreement)
31-Dec-2018
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Applicable
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
14-Jun-2042
Concession End Date (Actual) Actual end date of the concession
Not Applicable
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
50.44
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable