Project Details Project Details

Project Name
Road Upgradation (Arawali-Kante) Project
Project Brief
The project envisages four-laning of Arawali-Kante section from 241.30 km to 281.30 km on NH-66 (erstwhile-17) under NHDP Phase-IV on Hybrid Annuity Mode (HAM)
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
40.0 KM (Kilometer)
Location The geographical location of the project
Maharashtra
Type of PPP Variant of PPP model adopted for implementation of the project
Hybrid Annuity Mode (HAM)
Project Status
Pre-construction Stage
Concession Duration (In Months)
180
Bid Parameter Criteria adopted for award of project
Lowest Assessed Bid Price
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
As of July 2017, land acquisition was underway for the project.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
National Highways Authority of India (NHAI)
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
MEP Infrastructure Developers-Sanjose India Infrastructure & Construction (JV)
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
31-Mar-2016
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
20-Jan-2017
Appointed Date
Not Available
Construction Completion Date (as per Concession Agreement)
Not Available
Date to Start of Commercial Operation (as per Concession Agreement)
Not Available
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Applicable
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
30-Mar-2031
Concession End Date (Actual) Actual end date of the concession
Not Applicable
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
594.33
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.