Project Details Project Details

Project Name
Development of community centre and shopping complex at Kalyan
Project Brief
The project involves development of community centre and shopping complex at Lal Chowki, Kalyan in Thane district.
Sector
Social and Commercial Infrastructure
Sub-Sector
Tourism
Project Capacity
1.3 Acres
Location The geographical location of the project
Maharashtra
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Operate-Transfer (BOT)
Project Status
Under Construction
Concession Duration (In Months)
720
Bid Parameter Criteria adopted for award of project
Highest premium
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
As of March 2017, 80% project was completed.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Kalyan Dombivli Municipal Corporation
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
Dhanashree Developers Private Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
24-Sep-2008
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
Not Available
Construction Completion Date (as per Concession Agreement)
16-Jun-2010
Date to Start of Commercial Operation (as per Concession Agreement)
16-Jun-2010
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Applicable
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
23-Sep-2068
Concession End Date (Actual) Actual end date of the concession
Not Applicable
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
15.50
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable