Project Details Project Details

Project Name
Truck Terminal (First Avenue Business Park & Parking Plaza) (Kalyan) Project
Project Brief
The project involves setting up a truck terminal 'First Avenue Business Park & Parking Plaza' at Kalyan in Thane district. It includes construction, maintanance and operation of parking plaza, Ancillary structure, Octroi naka, Shopping centre, Weigh bridge and other structure.
Sector
Social and Commercial Infrastructure
Sub-Sector
Common infrastructure for industrial parks, SEZ
Project Capacity
Not Available
Location The geographical location of the project
Maharashtra
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Operate-Transfer (BOT)
Project Status
Under Construction
Concession Duration (In Months)
720
Bid Parameter Criteria adopted for award of project
Others
Other Bid Parameter Other bid parameter name
Highest Rent
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
Not Available

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Kalyan Dombivli Municipal Corporation
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
S M Associates and Rushi Construction Company
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
06-Jul-2005
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
09-Aug-2005
Construction Completion Date (as per Concession Agreement)
31-Dec-2015
Date to Start of Commercial Operation (as per Concession Agreement)
31-Dec-2015
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Applicable
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
05-Jul-2065
Concession End Date (Actual) Actual end date of the concession
Not Applicable
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
10.16
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.