Project Details Project Details

Project Name
Road Upgradation (Sriganganagar-Padampur-Raisinghnagar-Anupgarh) Project
Project Brief
The project involved construction of Sriganganagar- Padampur-Raisinghnagar- Anupgarh road from 36.90 Km. Ch.(SH-03) Km.2.00 to Km.38.90
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
36.9 KM (Kilometer)
Location The geographical location of the project
Rajasthan
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Operate-Transfer (BOT)
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
149
Bid Parameter Criteria adopted for award of project
Concession Duration
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
Not Available

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Public Works Department, Rajasthan
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
Deepak & Company, Sri Ganganagar
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
30-Nov-2011
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
22-Dec-2011
Construction Completion Date (as per Concession Agreement)
21-Sep-2012
Construction Completion Date (Actual) Actual Construction completion date
31-Aug-2012
Date to Start of Commercial Operation (as per Concession Agreement)
22-Sep-2012
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
04-Sep-2012
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
29-Mar-2024
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
17.57
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
17.57
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.