Project Details Project Details

Project Name
4 laning of Patna-Muzaffarpur stretch of NH77 from 0-46.3 km and construction of Muzzafarpur bypass on BOT(Annuity) Basis
Project Brief
The project involved four laning of Patna-Hajipur-Muzaffarpur section of NH-77 from 0.000 km to 46.300 km and construction of 16.87 km New Bypass connecting NH- 28 in Bihar under NHDP -III.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
46.3 KM (Kilometer)
Location The geographical location of the project
Bihar
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Operate-Transfer (BOT) Annuity
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
180
Bid Parameter Criteria adopted for award of project
Annuity
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
This is a PPPAC Recommended Project.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
National Highways Authority of India (NHAI)
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
Gammon Infrastructure Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
21-Feb-2010
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
09-Sep-2010
Appointed Date
10-Sep-2010
Construction Completion Date (as per Concession Agreement)
01-Sep-2016
Construction Completion Date (Actual) Actual Construction completion date
Not Available
Date to Start of Commercial Operation (as per Concession Agreement)
01-Sep-2016
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Available
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
28-Feb-2025
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
570.06
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.