Project Name
Berth No. 15 of New Western Dock for handling coal #
Project Brief
The project involved setting up a 1015 MW Coal Based Power Project near Padubidri in Udupi District of Karnataka state, which is about 37 Kms away from the New Mangalore Port. In order to make available coal at all times for the Power Project, UPCL proposed to utilize the port facilities of the NMPT by way of construction and operation of a captive Jetty along with associated facilities for handling bulk quantities of coal from various sources.
Sector
Transport
Sub-Sector
Ports (excluding captive)
Project Capacity
3.0 MTPA (Metric Tonne Per Annum)
Location The geographical location of the project
Karnataka
Type of PPP Variant of PPP model adopted for implementation of the project
Not Available
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
360
Bid Parameter Criteria adopted for award of project
Highest premium
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
Data is logically checked and corrected. Authority mentions the type of PPP as Captive Basis.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
New Mangalore Port Trust
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
Udupi Power Corporation Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
09-May-2008
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
30-May-2008
Appointed Date
Not Available
Construction Completion Date (as per Concession Agreement)
30-May-2011
Construction Completion Date (Actual) Actual Construction completion date
22-Jun-2012
Date to Start of Commercial Operation (as per Concession Agreement)
30-May-2011
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
22-Jun-2012
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
04-Sep-2038
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
230.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
376.52