Project Details Project Details

Project Name
Setting up of 24 MW Roura-II hydel power unit in Kinnaur district
Project Brief
The project involves setting up of Roura-II hydel power unit in Kinnaur district.
Sector
Energy
Sub-Sector
Renewable energy (grid)
Project Capacity
24.0 MW (Mega Watt)
Location The geographical location of the project
Himachal Pradesh
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Own-Operate-Manage (BOOM)
Project Status
Under Construction
Concession Duration (In Months)
480
Bid Parameter Criteria adopted for award of project
Others
Other Bid Parameter Other bid parameter name
MoU route with fixed royalty
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
Not Available

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Directorate of Energy, Himachal Pradesh
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
Roura Non Conventional Energy Private Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
19-Jun-2007
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
01-Oct-2010
Construction Completion Date (as per Concession Agreement)
30-Apr-2015
Date to Start of Commercial Operation (as per Concession Agreement)
30-Apr-2015
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Applicable
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
18-Jun-2049
Concession End Date (Actual) Actual end date of the concession
Not Applicable
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
246.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
159.20
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.