Project Details Project Details

Project Name
6 laning of Chenagapjalli to Start of Coimbatore bypass & 4 laning of end of Coimbatore bypass to TN/Kerala Boarder of NH 47
Project Brief
Six-laning from Chengapalli to start Coimbatore bypass (Section-1 from 102/035 km to 144/740 km on NH-47) and four-laning from End of Coimbatore Bypass to Tamil Nadu/Kerala Border (Section-2 from 170/940 km to 183/060 km on NH-47) in Tamil Nadu
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
54.8 KM (Kilometer)
Location The geographical location of the project
Multi State/ Centre
Type of PPP Variant of PPP model adopted for implementation of the project
Design-Build-Finance-Operate-Transfer (DBFOT)
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
324
Bid Parameter Criteria adopted for award of project
Highest premium
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
This is a PPPAC Recommended Project.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
National Highways Authority of India (NHAI)
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
IVRCL Chengapalli Tollways Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
25-Mar-2010
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
09-Sep-2010
Construction Completion Date (as per Concession Agreement)
07-Mar-2013
Construction Completion Date (Actual) Actual Construction completion date
14-Oct-2015
Date to Start of Commercial Operation (as per Concession Agreement)
08-Mar-2013
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
14-Oct-2015
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
24-Mar-2037
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
852.74
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.