Project Details Project Details

Project Name
Development of Four lane of Mangwan to MP/UP border section (km 98/2 to km 46/6) of NH 27 on DBFOT (Toll) basis
Project Brief
The project involves four laning on NH-27 road Mangawan-MP/UP Border in Rewa district.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
52.1 KM (Kilometer)
Location The geographical location of the project
Madhya Pradesh
Type of PPP Variant of PPP model adopted for implementation of the project
Design-Build-Finance-Operate-Transfer (DBFOT) Toll
Project Status
Under Construction
Concession Duration (In Months)
360
Bid Parameter Criteria adopted for award of project
Minimum grant
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
This is a VGF Final Approved Project.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Madhya Pradesh Road Development Corporation Limited (MPRDC)
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
M/s Topworth Tollways (Mangawan) Private Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
27-Apr-2012
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
13-Feb-2013
Appointed Date
15-Apr-2013
Construction Completion Date (as per Concession Agreement)
14-Apr-2015
Date to Start of Commercial Operation (as per Concession Agreement)
14-Apr-2015
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Applicable
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
26-Apr-2042
Concession End Date (Actual) Actual end date of the concession
Not Applicable
Project Grant
Type Of Grant
Construction Grant
Grant Amount in Rs Crore
46.97
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
381.66
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
410.70
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.