Project Name
Four laning of Orissa/Chhattisgarh Border - Aurang of NH-6 in length of 150.4 Km under NHDP-IV
Project Brief
The project involves four laning of Orissa/Chhattisgarh Border - Aurang NHDP-IV, NH-6, 88 Km to 239 Km.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
150.4 KM (Kilometer)
Location The geographical location of the project
Multi State/ Centre
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Operate-Transfer (BOT)
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
336
Bid Parameter Criteria adopted for award of project
Minimum grant
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
Not Available

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
National Highways Authority of India (NHAI)
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
BSCPL Aurang Tollway Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
25-Jan-2012
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
23-Jul-2012
Appointed Date
15-Feb-2013
Construction Completion Date (as per Concession Agreement)
13-Aug-2015
Construction Completion Date (Actual) Actual Construction completion date
Not Available
Date to Start of Commercial Operation (as per Concession Agreement)
13-Aug-2015
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Available
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
24-Jan-2040
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Construction Grant
Grant Amount in Rs Crore
30.00
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
1,232.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable