Project Details Project Details

Project Name
Four laning of Muzaffarnagar-Haridwar section of NH 58 from km 131 to 211 of NH 58 in the state of UP and Uttarakhand
Project Brief
The project involves four laning of Muzaffarnagar-Haridwar section on NH-58 from 131.0 km to 211.0 km in Uttar Pradesh and Uttarakhand under NHDP-III.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
80.0 KM (Kilometer)
Location The geographical location of the project
Multi State/ Centre
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Operate-Transfer (BOT)
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
300
Bid Parameter Criteria adopted for award of project
Minimum grant
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
This is a PPPAC Recommended Project. ERA-SIBMOST-Indian - Russian under consortium, Nicholas O'Dwyer and SA Infra- Ireland-India is Consultant.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
National Highways Authority of India (NHAI)
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
ERA-SIBMOST (JV)
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
24-Feb-2010
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
03-Sep-2010
Appointed Date
03-Sep-2010
Construction Completion Date (as per Concession Agreement)
01-Mar-2013
Construction Completion Date (Actual) Actual Construction completion date
Not Available
Date to Start of Commercial Operation (as per Concession Agreement)
01-Mar-2013
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Available
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
23-Feb-2035
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Available
Grant Amount in Rs Crore
123.59
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
804.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
1,563.55
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.