Project Details Project Details

Project Name
Four Laning of Maharashtra/Karnataka Border-Sangareddy Section from 348.0 km to 423.8 km on BOT (Toll)
Project Brief
The project involve four laning of Maharashtra/Karnataka Border-Sangareddy section from NH-9 from 348.0 km to 423.8 km and from 423.8 km to 493.0 km in Sangareddy district.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
145.0 KM (Kilometer)
Location The geographical location of the project
Multi State/ Centre
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Operate-Transfer (BOT)
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
300
Bid Parameter Criteria adopted for award of project
Highest premium
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
This is a PPPAC Recommended Project. Consultant: CDM Smith JV with Wilbur Smith, Indian.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
National Highways Authority of India (NHAI)
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
L&T Infrasructure Developement Projects Ltd
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
02-Feb-2012
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
27-Jun-2012
Appointed Date
01-Apr-2014
Construction Completion Date (as per Concession Agreement)
27-Sep-2016
Construction Completion Date (Actual) Actual Construction completion date
Not Available
Date to Start of Commercial Operation (as per Concession Agreement)
27-Sep-2016
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
Not Available
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
01-Feb-2037
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
1,273.30
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
1,544.18
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.