Project Details Project Details

Project Name
Development and Operation of Bikaner to Suratgarh section on NH 11 from km 553.869 to km 173.000 on NH 15
Project Brief
The project involves upgradation of Bikaner-Suratgarh Section of NH-15 from 553.9 km of NH-11 to 173.0 km of NH-15 via 10.6 km of NH-15 in Rajasthan.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
172.4 KM (Kilometer)
Location The geographical location of the project
Rajasthan
Type of PPP Variant of PPP model adopted for implementation of the project
Design-Build-Finance-Operate-Transfer (DBFOT)
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
192
Bid Parameter Criteria adopted for award of project
Highest premium
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
This is a VGF In Principle Approved Project.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Public Works Department, Rajasthan
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
MBL-SREI consortium
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
09-May-2012
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
16-Sep-2013
Appointed Date
16-Sep-2013
Construction Completion Date (as per Concession Agreement)
30-Jun-2018
Construction Completion Date (Actual) Actual Construction completion date
30-Jun-2018
Date to Start of Commercial Operation (as per Concession Agreement)
Not Available
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
30-Jul-2018
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
15-Sep-2029
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
2.51
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
501.08
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.