Project Details Project Details

Project Name
Four Laning of Devilalli Hassan Section of NH- 48 in the state of Karnataka under NHDP phase III A on BOT basis
Project Brief
The project involved 4/6-four laning of Devihalli-Hassan on NH-48 (km.110/000 to km.189/000) in Karnataka under NHDP-III A.
Sector
Transport
Sub-Sector
Roads and bridges
Project Capacity
79.0 KM (Kilometer)
Location The geographical location of the project
Karnataka
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Operate-Transfer (BOT) Toll
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
360
Bid Parameter Criteria adopted for award of project
Not Available
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
This is a PPPAC Recommended Project. Consultant: Lea Associates South Asia Pvt Ltd.

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
National Highways Authority of India (NHAI)
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
L&T Devihalli Hassan Tollway Limited
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
30-Apr-2010
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
14-Dec-2010
Construction Completion Date (as per Concession Agreement)
01-May-2013
Construction Completion Date (Actual) Actual Construction completion date
30-Nov-2013
Date to Start of Commercial Operation (as per Concession Agreement)
01-May-2013
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
30-Nov-2013
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
13-Dec-2040
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Available
Grant Amount in Rs Crore
180.00
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
440.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
Not Available
Project Cost (Actual) in Rs Crore Actual cost of the project
453.00
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.