Project Details Project Details

Project Name
Setting up of 24 MW Kut hydel power unit in Shimla district
Project Brief
The project involves setting up of 3x8 MW run-of-river Kut hydel power project in Shimla district.
Sector
Energy
Sub-Sector
Renewable energy (grid)
Project Capacity
24.0 MW (Mega Watt)
Location The geographical location of the project
Himachal Pradesh
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Own-Operate-Transfer (BOOT)
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
480
Bid Parameter Criteria adopted for award of project
Highest premium
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
Not Available

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Directorate of Energy, Himachal Pradesh
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
Goodwill energy enterprises
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
28-Apr-2007
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
26-May-2008
Construction Completion Date (as per Concession Agreement)
26-Nov-2013
Construction Completion Date (Actual) Actual Construction completion date
19-Dec-2018
Date to Start of Commercial Operation (as per Concession Agreement)
26-Nov-2013
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
19-Dec-2018
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
25-May-2048
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
192.19
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
189.50
Project Cost (Actual) in Rs Crore Actual cost of the project
Not Applicable
# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.