Project Details Project Details

Project Name
Gopalpur Port
Project Brief
Gopalpur Port [Ganjam district of Orissa]
Sector
Transport
Sub-Sector
Ports (excluding captive)
Project Capacity
54.0 MTPA (Metric Tonne Per Annum)
Location The geographical location of the project
Odisha
Type of PPP Variant of PPP model adopted for implementation of the project
Build-Own-Operate-Share-Transfer (BOOST)
Project Status
Operation and Maintenance Stage
Concession Duration (In Months)
420
Bid Parameter Criteria adopted for award of project
Revenue Share
Government/Non Government A government project pertains to project implemented either through traditional procurement mode or through PPP mode. A non-government project pertains to a project implemented solely by private sector
Government
Any Other Information
Not Available

Project Authority Name of the government agency that is the Concessioning Authority for the project
Name Of Authority
Department of Commerce and Transport, Odisha
Project Concessionaire The name of the concessionaire appointed for the project
Name Of Concessionaire
Consortium of Orissa Stevedores Ltd., Sara International Ltd., Noble group ltd.
Project Timelines
Concession Agreement Signing Date The date on which the concession agreement is signed
14-Sep-2006
Financial Closure Date The date on which the conditions precedent to the initial availability of funds under the Financing Agreements are fulfilled
Not Available
Appointed Date
Not Available
Construction Completion Date (as per Concession Agreement)
Not Available
Construction Completion Date (Actual) Actual Construction completion date
Not Available
Date to Start of Commercial Operation (as per Concession Agreement)
Not Available
Date to Start of Commercial Operation (Actual) Actual start date for commercial operation
29-Mar-2013
Concession End Date (as per Concession Agreement) The envisaged date of end of concession period as per the concession agreement
13-Sep-2041
Concession End Date (Actual) Actual end date of the concession
Not Available
Project Grant
Type Of Grant
Not Applicable
Grant Amount in Rs Crore
Not Available
Project Cost
Project Cost (as per Concession Agreement) in Rs Crore
6,500.00
Project Cost (Revised) in Rs Crore The project cost, if different from the cost as per the concession agreement
1,411.00
Project Cost (Actual) in Rs Crore Actual cost of the project
3,500.00