List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
2251 Setting up of 5 MW solar photovoltaic power unit at Ranipet in Vellore district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Bharat Heavy Electricals Limited Completed 50.00 01-Jun-2013 09-11-2016
2252 Setting up of 50 MW solar photovoltaic based power unit at Tiruchuli in Virudhunagar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu SEI Kathiravan Power Private Limited Completed 336.00 15-Nov-2015 09-11-2016
2253 Setting up of 50 MW solar photovoltaic power unit at Pokhran in Jaisalmer district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Today Energy (M P) Private Limited Completed 400.00 17-Dec-2014 09-11-2016
2254 Integrated Terminal Building (Goa) Government Infrastructure Projects (Traditional Procurement) Transport Airports Goa Airports Authority of India (AAI) Completed 380.10 06-May-2010 03-11-2016
2255 Construction of 400 kV MTPS Stage III-Arasur Line at Karamadai in Coimbatore District Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Tamil Nadu Tamil Nadu Transmission Corporation Limited Completed 132.11 28-Apr-2015 02-11-2016
2256 Establishment of 230/110- 33 kV substation at Alandur in Chennai District Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Tamil Nadu Tamil Nadu Generation and Distribution Corporation Limited Completed 68.22 29-Nov-2013 02-11-2016
2257 Two laning of bituminous Lalsot-Karauli road of NH-11B in Rajasthan under NHIIP Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Rajasthan Ministry of Road Transport and Highways Completed 310.00 26-Feb-2014 02-11-2016
2258 Widening and Strengthening of Draman-Sihunta-Chowari-Jot-Chamba-Bharmour Road from 0.00 km to 24.00 km at Draman Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Himachal Pradesh Public Works Department, Himachal Pradesh Completed 48.70 20-Nov-2009 02-11-2016
2259 45.8 km Road Upgradation (Una - Barsar - Bhota - Bhamla - Kalkhar - Ner Chowk) Project Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Himachal Pradesh Public Works Department, Himachal Pradesh Completed 141.92 29-Feb-2008 01-11-2016
2260 Airport (Raipur) Project - Expansion Government Infrastructure Projects (Traditional Procurement) Transport Airports Chhattisgarh Airports Authority of India (AAI) Completed 131.50 19-Sep-2008 01-11-2016
2261 Airport (Tirupati) Project - Modernisation (Phase I) Government Infrastructure Projects (Traditional Procurement) Transport Airports Andhra Pradesh Airports Authority of India (AAI) Completed 178.70 08-May-2013 01-11-2016
2262 Establishment of 400 kV substation at Thiruvalam in Vellore district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Tamil Nadu Tamil Nadu Generation and Distribution Corporation Limited Completed 99.91 11-Oct-2013 01-11-2016
2263 Establishment of 400/230 kV substation at Karamadai in Coimbatore district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Tamil Nadu Tamil Nadu Generation and Distribution Corporation Limited Completed 117.98 20-Aug-2014 01-11-2016
2264 Establishment of 400/230-110 kV substation at Kayathar in Tuticorin district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Tamil Nadu Tamil Nadu Generation and Distribution Corporation Limited Completed 114.94 30-Nov-2012 01-11-2016
2265 Khajuraho Airport Project - Modernisation Government Infrastructure Projects (Traditional Procurement) Transport Airports Madhya Pradesh Airports Authority of India (AAI) Completed 82.72 24-Dec-2009 01-11-2016
2266 Khukrana-Panipat DL Railway Line Project Government Infrastructure Projects (Traditional Procurement) Transport Railway track, tunnel, viaducts, bridges Haryana Northern Railway Completed 51.94 06-Jul-2008 01-11-2016
2267 Pir Pau Berth Project Government Infrastructure Projects (Traditional Procurement) Transport Ports (excluding captive) Maharashtra Mumbai Port Trust Completed 130.00 31-Oct-2012 01-11-2016
2268 Road Upgradation (Kamarhati - Sarahan-Nahan) Project Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Himachal Pradesh Public Works Department, Himachal Pradesh Completed 202.66 26-Oct-2009 01-11-2016
2269 Road Upgradation (Mubarikpur - Dehra- Ranital - Kotla) Project Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Himachal Pradesh Public Works Department, Himachal Pradesh Completed 69.73 18-Dec-2009 01-11-2016
2270 Road Upgradation (Una - Barsar - Bhota - Bhamla - Kalkhar - Ner Chowk) Project Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Himachal Pradesh Public Works Department, Himachal Pradesh Completed 115.83 29-Feb-2008 01-11-2016
2271 Setting up of 600 MW Coal Based Power Generating Unit (Stage III) at Mettur in Salem district Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Tamil Nadu Tamil Nadu Generation and Distribution Corporation Limited Completed 3,878.02 25-Jun-2008 01-11-2016
2272 Solar Photovoltic Power (Ichhawar) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Waneep Solar Private Limited Completed 450.00 12-Jun-2014 01-11-2016
2273 Substation (Kamuthi) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Tamil Nadu Tamil Nadu Transmission Corporation Limited Completed 161.76 01-Jul-2015 01-11-2016
2274 Water Supply Scheme (Dahod) Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline Gujarat Gujarat Urban Development Company Limited Completed 130.00 22-Dec-2011 01-11-2016
2275 Water Treatment Plant (Surajpura) Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water treatment plants Rajasthan Public Health Engineering Department, Rajasthan Completed 122.50 18-Mar-2013 01-11-2016
2276 Wind Based Power (Kukru) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Atria Power Corporation Limited Completed 350.00 17-Nov-2015 01-11-2016
2277 Wind Power (Thoseghar) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Rajasthan Gum Private Limited Completed 147.00 18-Oct-2014 01-11-2016
2278 Development of an IT park 'Spire Edge' - a Green Building Office Complex at Manesar in Gurgaon district Government Infrastructure Projects (Traditional Procurement) Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Haryana A N Buildwell Private Limited Completed 1,000.00 31-Dec-2008 31-10-2016
2279 Implementation of 142 km long water pipeline at Kalyan in Thane district Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline Maharashtra Kalyan Dombivli Municipal Corporation Completed 234.07 08-Nov-2011 31-10-2016
2280 Implementation of 220 kV Substation at Pimpalgaon in Nashik district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Maharashtra Maharashtra State Electricity Transmission Company Limited Completed 64.80 27-Aug-2009 31-10-2016
2281 Implementation of Sewerage Scheme in district 'E' of Allahabad Government Infrastructure Projects (Traditional Procurement) Water Sanitation Sewage collection, treatment and disposal system Uttar Pradesh Uttar Pradesh State Ganga River Conservation Agency Completed 142.00 05-Dec-2011 31-10-2016
2282 Implementation of Underground Sewerage Scheme of 12 MLD in Pudukkottai Municipality Government Infrastructure Projects (Traditional Procurement) Water Sanitation Sewage collection, treatment and disposal system Tamil Nadu Pudukkottai Municipality Completed 51.30 11-Feb-2008 31-10-2016
2283 Laying of 1000 Km long transmission line at Mundra in Kachchh district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Gujarat Adani Power Private Limited Completed 1,380.00 31-May-2009 31-10-2016
2284 Laying of 400 kV D/C Muzaffarpur-Susand Transmission Line in length of 87 CKM in Muzaffarpur district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Bihar IL&FS Energy Development Company Limited Completed 210.70 01-Jan-2015 31-10-2016
2285 Modernisation of 120MW Harduaganj Coal Based Power Unit 7 in Aligarh district Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Uttar Pradesh Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited Completed 231.71 31-Aug-2011 31-10-2016
2286 Setting up of 10 MW Solar Power unit at Bali in Pali district under JNNSM Phase II-Batch I Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Laxmi Diamond Private Limited Completed 70.00 28-Mar-2015 31-10-2016
2287 Setting up of 10 MW Solar Power unit at Gurha in Bikaner district under JNNSM Phase I-Batch II Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Sai Maithili Power Company Private Limited Completed 70.00 25-Jan-2012 31-10-2016
2288 Setting up of 10 MW Solar Power Unit at Kamalapuram in Tuticorin district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu TN Solar Energy Private Limited Completed 70.00 30-Apr-2015 31-10-2016
2289 Setting up of 10 MW Solar Power unit at Mangoon in Perambalur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu SEI Adityashakti Private Limited Completed 70.00 31-Dec-2014 31-10-2016
2290 Setting up of 10 MW Solar Power unit at Nimbahera in Bhilwara district under JNNSM Phase II Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan RDA Energy Private Limited Completed 70.00 25-Jan-2012 31-10-2016
2291 Setting up of 10 MW Solar Power unit at Pokaran in Jaisalmer district under JNNSM Phase II Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Palimarwar Solar Project Private Limited Completed 70.00 28-Mar-2014 31-10-2016
2292 Setting up of 140 MW Solar Power unit at Bhadla in Jodhpur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Essel Mining & Industries Limited Completed 140.00 28-Mar-2013 31-10-2016
2293 Setting up of 15 MW Wind Power unit at Kayathar in Tuticorin district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Atria Power Corporation Limited Completed 250.00 17-Nov-2015 31-10-2016
2294 Setting up of 15 MW Solar Power unit at Monjanur in Karur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Swelect Energy Systems Limited Completed 105.00 31-Jan-2013 31-10-2016
2295 Setting up of 18 MW Coal Based Power plant in Valsad district Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Gujarat Atul Limited Completed 144.00 30-Apr-2015 31-10-2016
2296 Setting up of 20 MW Solar Power unit at Bari Sid in Jodhpur district - Medha Energy Private Limied Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Medha Energy Private Limied Completed 140.00 28-Mar-2014 31-10-2016
2297 Setting up of 30 MW Solar Power unit at Kalyan Singh Ki Sid in Jodhpur district under JNNSM Phase II Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan SEI Suryalabh Private Limited Completed 210.00 25-Jan-2012 31-10-2016
2298 Setting up of 31.5 MW Solar Power unit at Mirpur Lalan in Mansa district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Punjab Bhanu Energy Infrastructure & Power Limited Completed 200.00 30-Jun-2014 31-10-2016
2299 Setting up of 4 MW Periyar Vaigai-III Small Hydro Electric Power Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Tamil Nadu Generation and Distribution Corporation Limited Completed 75.00 31-May-2011 31-10-2016
2300 Setting up of 40 MW Solar Power Unit at Moolippatti in Virudhunagar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Giriraj Enterprises Completed 250.00 31-Dec-2014 31-10-2016
2301 Setting up of 5 MW Solar Photovoltaic Power Project at Bhachau in Kachchh Distrct Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Euro Solar Power Private Limited Completed 50.00 01-Aug-2011 31-10-2016
2302 Setting up of 5 MW Solar Photovoltaic Power Project at Charanka in Patan Distrct Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat GSPC Pipavav Power Company Limited Completed 50.00 01-Dec-2011 31-10-2016
2303 Setting up of 5 MW Solar Photovoltaic Power Project at Fatepur in Surendranagar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat EMCO Limited Completed 50.00 01-Oct-2011 31-10-2016
2304 Setting up of 5 MW Solar Photovoltaic Power Project in Patan Distrct Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Jaihind Projects Limited Completed 50.00 15-Dec-2012 31-10-2016
2305 Setting up of 5 MW Solar Power Project at Shiv Lakhash in Kachchh district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Backbone Enterprises Limited Completed 70.00 02-Dec-2011 31-10-2016
2306 Setting up of 50 MW Solar Photovoltaic Power Project in Sabarkantha district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Aatash Power Private Limited Completed 500.00 15-Dec-2012 31-10-2016
2307 Setting up of 50 MW Solar Power unit at That in Jaisalmer district under JNNSM Phase II-Batch I Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Today Green Energy Private Limited Completed 350.00 28-Mar-2014 31-10-2016
2308 Setting up of 8 MW Solar Power Unit at Muthuramalingapuram in Virudhunagar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu TN Solar Energy Private Limited Completed 56.00 30-Apr-2015 31-10-2016
2309 Setting up of 9 MW Solar Photovoltaic Power Project in Kachchh Distrct Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Integrated Coal Mining Limited Completed 110.00 01-Sep-2011 31-10-2016
2310 Water Treatment Plant (Netivli Hill) Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water treatment plants Maharashtra Kalyan Dombivli Municipal Corporation Completed 106.81 02-Mar-2009 31-10-2016
2311 Power Transmission (Barpeta) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 146.50 09-Jan-2009 18-10-2016
2312 Power Transmission (Cachar) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 74.62 05-Mar-2007 18-10-2016
2313 Power Transmission (Darrang) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 164.10 24-Sep-2008 18-10-2016
2314 Power Transmission (Dhubri) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 184.64 09-Jan-2009 18-10-2016
2315 Power Transmission (Dibrugarh) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 100.42 06-Feb-2009 18-10-2016
2316 Power Transmission (Golaghat) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 109.08 16-Sep-2008 18-10-2016
2317 Power Transmission (Jorhat) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 84.65 16-Jun-2008 18-10-2016
2318 Power Transmission (Kamrup) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 199.28 16-Feb-2009 18-10-2016
2319 Power Transmission (Karbi Anglong) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 458.83 30-Jan-2009 18-10-2016
2320 Power Transmission (Karimganj) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 59.85 14-May-2009 18-10-2016
2321 Power Transmission (Lakhimpur) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 132.45 02-Mar-2009 18-10-2016
2322 Power Transmission (Morigaon) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 62.18 09-Jun-2008 18-10-2016
2323 Power Transmission (Nagaon) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 158.44 08-Jan-2009 18-10-2016
2324 Power Transmission (Nalbari) Project - RGGVY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 84.44 14-Jun-2008 18-10-2016
2325 Power Transmission (Pallatana-Silchar-Bongariagaon) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Electricity Grid Corporation Limited Completed 200.00 28-Sep-2012 18-10-2016
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.