This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
2176 Setting up of 10 MW bagasse based power unit at Hasanpur in Samastipur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Bihar Hasanpur Sugar Mills Completed 50.00 28-Feb-2014 28-11-2016
2177 Setting up of 10 MW solar based power unit in Bagalkot district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Azure Power India Private Limited Completed 100.00 31-Aug-2013 28-11-2016
2178 Setting up of 10 MW solar based power unit in Durg district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Chhattisgarh Azure Power India Private Limited Completed 102.00 30-Jun-2014 28-11-2016
2179 Setting up of 10 MW solar photovoltaic based power unit at Musiri in Tiruchchirappalli district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Swelect Energy Systems Limited Completed 100.00 28-Feb-2015 28-11-2016
2180 Setting up of 10 MW waste heat recovery based power unit at Bojireddypalli, Yadiki in Anantappur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Penna Cement Industries Limited Completed 100.00 22-Nov-2014 28-11-2016
2181 Setting up of 100 MW solar power unit at Sardargarh and Chughe Kalan in Bhatinda district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Punjab Adani Green Energy Limited Completed 640.00 31-Jan-2015 28-11-2016
2182 Setting up of 100 MW wind power unit at Basavana in Bijapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Fortune Five Hydel Projects Private Limited Completed 500.00 30-Sep-2012 28-11-2016
2183 Setting up of 100 MW wind power unit in Satara district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Greenko Group Completed 500.00 30-Jun-2011 28-11-2016
2184 Setting up of 1080 MW captive lignite based power plant in Barmer district Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Rajasthan Raj West Power Limited Completed 6,085.00 30-May-2007 28-11-2016
2185 Setting up of 11.5 MW rooftop solar based power unit at Dera Baba Jaimal Singh in Amritsar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Punjab Radha Soami Satsang Beas Completed 139.00 31-Dec-2013 28-11-2016
2186 Setting up of 12 MW wind power unit in Jaisalmer district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Malpani Group Completed 60.00 30-Nov-2011 28-11-2016
2187 Setting up of 12.5 MW waste based power unit at Gummidipoondi in Tiruvallur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Bhatia International Limited Completed 62.50 31-Jan-2011 28-11-2016
2188 Setting up of 15 MW biomass based power unit at Piduru in Nellore district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Bhanu Prakash Power Projects Private Limited Completed 75.00 28-Feb-2011 28-11-2016
2189 Setting up of 15 MW biomass based power unit in Chhindwara district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Shalivahana Green Energy Limited Completed 75.00 30-Jun-2010 28-11-2016
2190 Setting up of 15 MW solar based power unit in Banaskantha district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Eelctrotherm India Limited Completed 700.00 31-Jul-2011 28-11-2016
2191 Setting up of 15 MW solar photovoltaic power unit at Gunthavada in Banas Kantha district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Moser Baer Energy & Development Limited Completed 150.00 30-Aug-2011 28-11-2016
2192 Setting up of 18 MW solar based power unit in Madurai district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu CESC Limited Completed 180.00 30-Jun-2015 28-11-2016
2193 Setting up of 18.9 MW wind based power unit at Tallimadugula in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Suzlon Energy Limited Completed 94.50 31-Oct-2014 28-11-2016
2194 Setting up of 25 MW solar photovoltaic power unit in Patan district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat SunClean Renewable Power Private Limited Completed 250.00 30-Aug-2012 28-11-2016
2195 Setting up of 30 MWp solar photovoltaic based power unit at Maddur in Mahaboob Nagar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Telangana ACME Cleantech Solutions Limited Completed 300.00 31-Jan-2015 28-11-2016
2196 Setting up of 32 MW wind power unit at Chinchani in Belgaum district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Doddanavar Global Energy Private Limited Completed 160.00 31-Aug-2011 28-11-2016
2197 Setting up of 35 MW solar photovoltaic power unit in Gandhinagar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Lanco Solar Energy Private Limited Completed 350.00 31-Dec-2011 28-11-2016
2198 Setting up of 40 MW solar based power unit at Lolada Sami in Patan district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat PLG Power Limited Completed 700.00 31-Dec-2010 28-11-2016
2199 Setting up of 44 MW bagasse based power unit at Panhala in Kolhapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Urjankur Shree Tatyasaheb Kore SSK Limited Completed 220.00 31-Dec-2010 28-11-2016
2200 Setting up of 44 MW bagasse based power unit at Warananagar in Kolhapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shree Warana SSK Limited Completed 220.00 31-Dec-2009 28-11-2016
2201 Setting up of 44 MW wind based power unit at Tadas in Haveri district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Lalpur Wind Energy Private Limited Completed 220.00 24-Feb-2015 28-11-2016
2202 Setting up of 5 MW solar photovoltaic power unit at BAP, Phalodi in Nagaur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Greentech Power Private Limited Completed 55.00 13-Dec-2011 28-11-2016
2203 Setting up of 5 MW solar photovoltaic power unit at Bawdi Barsinga in Jodhpur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Kanoria Chemicals & Industries Limited Completed 67.50 22-Dec-2011 28-11-2016
2204 Setting up of 5 MW solar photovoltaic power unit at Bhojas in Nagaur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan DDE Renewable Energy Limited Completed 60.00 12-Dec-2011 28-11-2016
2205 Setting up of 5 MW solar photovoltaic power unit at Dhank in Rajkot district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Aravali Infrapower Limited Completed 62.50 22-Dec-2011 28-11-2016
2206 Setting up of 5 MW solar photovoltaic power unit at Karjat in Raigarh district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Camelot Enterprises Private Limited Completed 50.00 02-Mar-2012 28-11-2016
2207 Setting up of 5 MW solar photovoltaic power unit at Khinvsar in Nagaur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Finehope Allied Engineering Private Limited Completed 53.00 13-Dec-2011 28-11-2016
2208 Setting up of 5 MW solar photovoltaic power unit at Lanwain in Jaisalmer district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Amrit Energy Private Limited Completed 57.50 15-Dec-2011 28-11-2016
2209 Setting up of 5 MW solar photovoltaic power unit Deh in Bikaner district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan SunEdison Energy India Private Limited Completed 52.00 14-Dec-2011 28-11-2016
2210 Setting up of 5 MW solar photovoltaic power unit in Barmer district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Vasavi Solar Power Private Limited Completed 69.00 13-Dec-2011 28-11-2016
2211 Setting up of 5 MW solar photovoltaic power unit in Jaisalmer district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Newton Solar Private Limited Completed 52.00 30-Oct-2011 28-11-2016
2212 Setting up of 5 MW solar photovoltaic power unit in Nagaur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Electromech Maritech Private Limited Completed 70.00 13-Dec-2011 28-11-2016
2213 Setting up of 5 MW solar photovoltaic power unit in Patan district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Z F Steering Gear India Limited Completed 65.00 30-Sep-2012 28-11-2016
2214 Setting up of 50 MW solar based power unit in Kachchh district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Muni Seva Ashram Completed 250.00 30-May-2011 28-11-2016
2215 Setting up of 50 MW solar based power unit in Virudhunagar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu SEI Phoebus Private Limited Completed 350.00 31-Jan-2015 28-11-2016
2216 Setting up of 54 MW coal based power unit at Rajgangpur in Sundargarh district Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Odisha OCL India Limited Completed 324.00 30-Jun-2009 28-11-2016
2217 Setting up of 6.5 MW waste heat recovery based power unit at Rabriyawas in Pali district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Ambuja Cements Limited Completed 92.00 28-May-2015 28-11-2016
2218 Setting up of 7 MW waste heat recovery based power unit at Boincheruvupalli in Kurnool district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Rain Cements Limited Completed 70.00 15-Sep-2015 28-11-2016
2219 Setting up of 9 MW solar based power unit at Vedachandur in Madurai district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Gamesa Wind Turbines Private Limited Completed 90.00 31-Jan-2015 28-11-2016
2220 Two laning of J K Pur-Muniguda-Bhawanipatna border road in 80.5 Km length in Rayagada district Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Odisha Public Works Department, Odisha Completed 121.00 31-Oct-2010 28-11-2016
2221 Construction of Mysore-Chamarajanagar GC Railway Line in Length of 148 Km Government Infrastructure Projects (Traditional Procurement) Transport Railway track, tunnel, viaducts, bridges Karnataka South Western Railway Completed 608.58 22-Apr-2003 21-11-2016
2222 Development of 15.1 CBM, Utari dam in Lalitpur district. Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Uttar Pradesh Irrigation Department, Uttar Pradesh Completed 210.04 30-Sep-2008 21-11-2016
2223 Setting up of 16 MW of wind power unit in Patan district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Oil India Limited Completed 126.50 Not Available 10-11-2016
2224 Construction of road over bridge between Layalpur-Khalsa College Halt in Jullandhar district Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Punjab Northern Railway Completed 50.86 31-May-2005 09-11-2016
2225 Development of a liquid terminal with a capacity of 120000 KL at Pipavav in Gujarat - Phase I Government Infrastructure Projects (Traditional Procurement) Transport Ports (excluding captive) West Bengal Aegis Logistics Limited Completed 123.00 30-Nov-2013 09-11-2016
2226 Development of a liquid terminal with a capacity of 60190 KL at Chiranjibpur, Haldia in Purba Medinipur district Government Infrastructure Projects (Traditional Procurement) Transport Ports (excluding captive) West Bengal Aegis Logistics Limited Completed 51.00 31-Dec-2012 09-11-2016
2227 Development of an integrated shipyard-cum-port complex at Kattupalli village in Tiruvallur district Government Infrastructure Projects (Traditional Procurement) Transport Ports (excluding captive) Tamil Nadu Tamil Nadu Industrial Development Corporation Limited Completed 4,000.00 31-Aug-2010 09-11-2016
2228 Expansion of airport at Kempegowda international airport, Devanahalli in Bangalore district Government Infrastructure Projects (Traditional Procurement) Transport Airports Karnataka Bangalore International Airport Limited Completed 1,500.00 30-Jun-2011 09-11-2016
2229 Expansion of bagasse based power unit from 10 MW to 30 MW at Venunagar in Solapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shri Vithal SSK Limited Completed 100.00 30-Sep-2014 09-11-2016
2230 Expansion of bagasse based power unit from 15 MW to 31.5 MW in Solapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Lokmangal Sugar Ethanol & Cogeneration Industries Limited Completed 82.50 30-Jun-2010 09-11-2016
2231 Expansion of LPG import/ export terminal capacity from 31,500 tonnes to 36,900 tonnes at Kasberia in Midnapore district Government Infrastructure Projects (Traditional Procurement) Energy Oil/ Gas/ LNG Storage West Bengal Indian Oil Petronas Private Limited Completed 75.00 31-Dec-2015 09-11-2016
2232 Implementation of Mahuar medium irrigation scheme in Shivpuri district Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Madhya Pradesh Water Resources Department, Madhya Pradesh Completed 233.13 06-Aug-2011 09-11-2016
2233 Jakhal-Mansa DL Railway Line Project Government Infrastructure Projects (Traditional Procurement) Transport Railway track, tunnel, viaducts, bridges Multi State/ Centre Northern Railway Completed 165.00 30-Apr-2008 09-11-2016
2234 Renovation of existing 100 MW Kopili hydel power project in Dima Hasao district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Assam North Eastern Electric Power Corporation Limited Completed 50.92 12-Dec-2013 09-11-2016
2235 Renovation of existing 20.4 MW Pathri hydel power project in Haridwar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Uttarakhand UJVN Limited Completed 113.25 09-Mar-2010 09-11-2016
2236 Renovation of existing 32 MW Poringalkurthu hydel power project in Thrissur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Kerala Kerala State Electricity Board Completed 88.63 23-Dec-2011 09-11-2016
2237 Setting up of 10 MW bagasse based power unit at Akkalkot in Solapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Matoshri Laxmi Sugar Co-generation Industries Limited Completed 50.00 30-Jun-2012 09-11-2016
2238 Setting up of 10 MW bagasse based power unit at Sohagpur in Betul district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Shree Durga Khandsari (Sugar) Mills Completed 50.00 26-Aug-2014 09-11-2016
2239 Setting up of 10 MW biomass based power unit at Bharouli in Umaria district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Shalivahana (Biomass) Power Projects Limited Completed 50.00 30-Apr-2010 09-11-2016
2240 Setting up of 10 MW biomass power plant at Deoli in Wardha district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Maharashtra Vidyut Nigam Limited Completed 50.00 30-Jun-2009 09-11-2016
2241 Setting up of 15 MW co-generation power unit at Mahatma Fule Nagar (Bijwadi) in Pune district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Karmyogi Shankarraoji Patil SSK Limited Completed 75.00 30-Nov-2011 09-11-2016
2242 Setting up of 15 MW solar based power unit in Virudhunagar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu RT Renewable Energy Private Limited Completed 105.00 30-Jun-2015 09-11-2016
2243 Setting up of 17.5 MW new bagasse based power unit at Kuditre in Kolhapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Kumbhi Kasari SSK Limited Completed 71.59 03-Aug-2012 09-11-2016
2244 Setting up of 18 MW bagasse based power unit at Mahatmafule Nagar in Aurangabad district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Baramati Agro Limited Completed 90.00 31-Jan-2013 09-11-2016
2245 Setting up of 18 MW bagasse based power unit at Vilasnagar in Latur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Manjara Shetkari SSK Limited Completed 87.00 31-Jan-2011 09-11-2016
2246 Setting up of 18 MW co-generation power unit at Shahajinagar in Pune district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Nira Bhima SSK limited Completed 90.00 28-Feb-2013 09-11-2016
2247 Setting up of 21 MW bagasse based power unit at Pangari in Bid district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Vaidyanath SSK Limited Completed 110.00 31-Dec-2010 09-11-2016
2248 Setting up of 22 MW bagasse based power unit at Belewadi Kalmma in Kolhapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Sar Senapati Santaji Ghorpade Sugar Factory Limited Completed 110.00 31-Jan-2012 09-11-2016
2249 Setting up of 22 MW bagasse based power unit at Sundernagar in Bid district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Majalgaon SSK Limited Completed 113.00 30-Apr-2012 09-11-2016
2250 Setting up of 30 MW co-generation power unit at Lohara in Osmanabad district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Lokmangal Mauli Industries Limited Completed 150.00 31-Jul-2010 09-11-2016
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.