This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
156 Laying of 1000 Km long transmission line at Mundra in Kachchh district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Gujarat Adani Power Private Limited Completed 1,380.00 31-May-2009 31-10-2016
157 40 MW Solar Power (Banaskantha) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Adani Power Private Limited Completed 700.00 30-Sep-2010 01-12-2015
158 1320 MW Coal Based Power (Kawai) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Rajasthan Adani Power Rajasthan Limited Completed 5,889.00 20-Jan-2010 16-12-2015
159 Setting up of 20 MW solar power unit at Hubballi in Dharwad Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Aditya Birla Nuvo Limited Under Construction 178.00 14-Dec-2016 13-03-2017
160 Setting up of 20 MW solar power unit at Mullenger in Bengaluru Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Aditya Birla Nuvo Limited Under Construction 200.00 14-Dec-2016 13-03-2017
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.