List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9242 Total Project Cost(in Rs Crore): 6,813,008.32
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
781 Setting up of 45 MW Lower Pachuk-II hydel power unit in Kameng # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 315.00 27-Aug-2010 30-10-2019
782 Setting up of 45 MW Tirap hydel power unit in Changlang # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 315.00 16-Apr-2013 30-10-2019
783 Setting up of 46 MW Digin hydel power unit in West Kameng # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 322.00 15-Nov-2010 30-10-2019
784 Setting up of 46 MW Sepia hydel power unit in Arunachal Pradesh # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 322.00 25-Oct-2007 30-10-2019
785 Setting up of 48 MW Ithun-II hydel power unit in Lower Dibang Valley # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 336.00 29-Nov-2008 30-10-2019
786 Setting up of 48 MW Lower Marjingla hydel power unit in East Kameng # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 336.00 27-Aug-2010 30-10-2019
787 Setting up of 48 MW Papu Valley hydel power unit in East Kameng # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 345.60 25-Nov-2008 30-10-2019
788 Setting up of 5.4 MW Sarbari-II small hydel power unit in Kullu district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 46.00 15-Mar-2001 30-10-2019
789 Setting up of 50 MW Tsa Chu-ILower hydel power unit in Tawang # * Government Infrastructure Projects (PPP) Energy Electricity transmission Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 350.00 27-Aug-2010 30-10-2019
790 Setting up of 500 MW Emini hydel power unit in Dibang Valley district # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 3,500.00 02-Mar-2009 30-10-2019
791 Setting up of 55 MW Para hydel power unit in Kameng # * Government Infrastructure Projects (PPP) Energy Electricity transmission Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 385.00 19-Nov-2008 30-10-2019
792 Setting up of 552 MW Dengser hydel power unit in Upper Subansiri # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 3,864.00 26-Apr-2011 30-10-2019
793 Setting up of 56 MW Taiyong hydel power unit in West Siang # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 392.00 06-Jun-2011 30-10-2019
794 Setting up of 6 MW Baner hydel power unit in Kangra district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 54.59 29-May-2000 30-10-2019
795 Setting up of 60 MW Marjingla hydel power unit in East Kameng # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 432.00 12-Jan-2008 30-10-2019
796 Setting up of 60 MW Pachuk-II hydel power unit in Kameng # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 420.00 12-Jan-2008 30-10-2019
797 Setting up of 600 MW Kameng-II hydel power unit in West Kameng district # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 4,200.00 23-Nov-2006 30-10-2019
798 Setting up of 63 MW Dardu hydel power unit in Papum Pare# * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 463.00 26-Dec-2007 30-10-2019
799 Setting up of 66 MW Simang-II hydel power unit in East Siang # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 475.20 06-Feb-2008 30-10-2019
800 Setting up of 67 MW Simang-I hydel power unit in East Siang # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 469.00 06-Feb-2008 30-10-2019
801 Setting up of 68 MW Tidding-II hydel power unit in Arunachal Pradesh # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 496.40 26-Feb-2009 30-10-2019
802 Setting up of 680 MW Attunli hydel power unit in Dibang Valley district # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 7,158.84 08-Dec-2008 30-10-2019
803 Setting up of 70 MW Badao hydel power unit in Kameng # * Government Infrastructure Projects (PPP) Energy Electricity transmission Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 490.00 19-Nov-2008 30-10-2019
804 Setting up of 70 MW Budhil hydel power unit in Chamba district # Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 418.80 23-Sep-2004 30-10-2019
805 Setting up of 700 MW Tato-II hydel power unit in West Siang district# * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 6,000.00 22-Feb-2006 30-10-2019
806 Setting up of 74 MW Tagurshit hydel power unit at Tado Gitu in West Siang # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 518.00 23-Dec-2008 30-10-2019
807 Setting up of 75 MW Chela hydel power unit in Arunachal Pradesh # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 525.00 14-Feb-2013 30-10-2019
808 Setting up of 780 MW Nyamjang Chhu hydel power unit in Tawang # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 6,852.28 28-May-2009 30-10-2019
809 Setting up of 8 MW hydel power unit at Kurmi in Shimla district # Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 68.49 19-Jun-2007 30-10-2019
810 Setting up of 8 MW Rima hydel power unit in Changlang # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 57.60 02-Mar-2009 30-10-2019
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.