List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
571 Hydro Electric Power (Junnar) Project Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Water Resources Department, Maharashtra Operation and Maintenance Stage 15.62 28-May-2009 01-11-2019
572 Hydro Electric Power (Kadavi) Project Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Water Resources Department, Maharashtra Completed 7.20 23-Mar-2007 01-11-2019
573 Hydro Electric Power (Kumbhi) Project Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Water Resources Department, Maharashtra Operation and Maintenance Stage 12.00 21-Jul-2006 01-11-2019
574 Hydro Electric Power (Mukane) Project Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Water Resources Department, Maharashtra Completed 7.32 01-Oct-2010 01-11-2019
575 Hydro Electric Power (Nisare) Project Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Water Resources Department, Maharashtra Pre-construction Stage 10.80 06-Jan-2012 01-11-2019
576 Hydro Electric Power (Parseoni) Project - Package 1 Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Water Resources Department, Maharashtra Operation and Maintenance Stage 6.72 20-Oct-2007 01-11-2019
577 Hydro Electric Power (Parseoni) Project - Package 2 Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Water Resources Department, Maharashtra Operation and Maintenance Stage 32.94 22-Oct-2007 01-11-2019
578 Hydro Electric Power (Patgaon) Project Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Water Resources Department, Maharashtra Operation and Maintenance Stage 12.00 30-Jul-2006 01-11-2019
579 Hydro Electric Power (Satara) Project Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Water Resources Department, Maharashtra Operation and Maintenance Stage 7.50 01-Feb-2013 01-11-2019
580 Hydro Electric Power (Temghar) Project Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Water Resources Department, Maharashtra Completed 26.24 25-Jul-2011 01-11-2019
581 Hydro Electric Power (Urmodi) Project Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Water Resources Department, Maharashtra Operation and Maintenance Stage 14.40 26-Feb-2013 01-11-2019
582 Hydro Electric Power (Waghur) Project Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Water Resources Department, Maharashtra Operation and Maintenance Stage 7.89 20-Aug-2010 01-11-2019
583 Hydro Electric Power (Waki) Project Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Water Resources Department, Maharashtra Under Construction 6.54 11-Oct-2010 01-11-2019
584 Kilhi-Bahl Hydel Power Project # Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Pre-construction Stage 21.00 02-Jun-2011 01-11-2019
585 Kurhed Hydel Power Project - Stage II # Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Pre-construction Stage 58.27 24-Oct-2009 01-11-2019
586 Kurpan Hydel Power Project - Stage III # Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Pre-construction Stage 122.14 12-Jan-2005 01-11-2019
587 Kuwarsi Hydel Power Project - Stage II Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 95.79 25-Jul-2009 01-11-2019
588 Laxman Mandwa Small Hydro Power Project * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Madhya Pradesh Narmada Valley Development Authority Not Available 25.00 Not Available 01-11-2019
589 Madho-I Small Hydel Power Project # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Uttar Pradesh Uttar Pradesh Jal Vidyut Nigam Limited Pre-construction Stage 45.97 30-Nov-2011 01-11-2019
590 Madho-II Small Hydel Power Project # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Uttar Pradesh Uttar Pradesh Jal Vidyut Nigam Limited Pre-construction Stage 23.05 30-Nov-2011 01-11-2019
591 Malana Hydel Power Project - Stage III # Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Pre-construction Stage 212.66 26-May-2011 01-11-2019
592 Mandsaur Wind Power Project in Madhya Pradesh Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Madhya Pradesh Marut-Shakti Energy India Limited Operation and Maintenance Stage 326.00 Not Available 01-11-2019
593 Miyar Hydel Power Project # Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Pre-construction Stage 1,125.16 22-Mar-2011 01-11-2019
594 Muzaffarpur -Sursand Transmission Line * Government Infrastructure Projects (PPP) Energy Electricity transmission Bihar Power Grid Corpn. of India Ltd. Under Construction 210.70 09-Jul-2012 01-11-2019
595 Nazeerabad Wind Farm, Mytrah Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Telangana Operation and Maintenance Stage 795.00 Not Available 01-11-2019
596 Nesang Hydel Power Project # Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Pre-construction Stage 70.00 12-Oct-2011 01-11-2019
597 Nirgajini Small Hydel Power Project * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Uttar Pradesh Uttar Pradesh Jal Vidyut Nigam Limited Pre-construction Stage 108.43 31-Dec-2015 01-11-2019
598 Northern Region System Strengthening Scheme (NRSS-XXXI (Part-B) * Government Infrastructure Projects (PPP) Energy Electricity transmission Multi State/ Centre REC Transmission Projects Company Limited Under Construction 200.00 Not Available 01-11-2019
599 Panan Hydro Power project # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Sikkim Sikkim Power Development Corporation Limited Pre-construction Stage 2,021.90 05-Dec-2005 01-11-2019
600 Parbati Hydel Power Project # Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Pre-construction Stage 78.35 12-Jan-2005 01-11-2019
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.