List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
241 | Setting up of 850 MW hydel power unit at Kishtwar in Doda district * | Government Infrastructure Projects (PPP) | Energy | Renewable energy (grid) | Jammu & Kashmir | Jammu and Kashmir State Power Development Corporation Limited | Under Construction | 5,500.00 | 11-Mar-2010 | 01-11-2019 |
242 | Mauda/Nagpur Power Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Maharashtra | NTPC Limited | Completed | 5,500.00 | Not Available | 22-06-2019 |
243 | Natural Gas Pipeline (Vijaipur-Dadri-Bawana) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Gas pipelines | Multi State/ Centre | GAIL (India) Limited | Completed | 5,500.00 | 15-Jun-2008 | 27-09-2015 |
244 | Nagarjuna Power Project | Government Infrastructure Projects (PPP) | Energy | Electricity Distribution | Karnataka | Karnataka Power Transmission Corporation Limited (KPTCL) | Operation and Maintenance Stage | 5,496.00 | Not Available | 30-10-2019 |
245 | Bharat Sanchar Nigam Limited 2014-15 | Government Infrastructure Projects (PPP) | Communication | Telecommunication Network and Services | Multi State/ Centre | Department of Telecom | Operation and Maintenance Stage | 5,446.24 | Not Available | 21-06-2019 |
246 | Simhadri Coal Based Power Project - Stage II | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Andhra Pradesh | NTPC Limited | Completed | 5,401.17 | 30-Mar-2007 | 22-06-2019 |
247 | Implementation of Sripada Yellampalli irrigation project in Karimnagar district* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Telangana | Irrigation and CAD Department, Telangana | Under Construction | 5,400.00 | 28-Jul-2004 | 22-11-2019 |
248 | Setting up of 500 MW Teesta-VI hydel power unti in Southern Sikkim # | Government Infrastructure Projects (PPP) | Energy | Renewable energy (grid) | Sikkim | Sikkim Power Development Corporation Limited | Under Construction | 5,400.00 | 07-Dec-2005 | 01-11-2019 |
249 | Implementation of Mulwad lift irrigation scheme stage-III on 560929.2 acres in Bijapur | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Karnataka | Krishna Bhagya Jala Nigam Limited | Under Construction | 5,398.55 | 30-Nov-2012 | 01-03-2017 |
250 | Six laning of Kishangarh -Udaipur- Ahmedabad section of NH 79A, NH79, NH 76 and NH 8 under NHDP Phase V, length 555.50 km | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Rajasthan | Ministry of Road Transport and Highways | Operation and Maintenance Stage | 5,387.30 | 01-Sep-2016 | 20-11-2019 |
251 | Implementation of 1000 MW coal based power unit at Sagardighi | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | West Bengal | West Bengal Power Development Corporation Limited | Completed | 5,340.00 | 22-Feb-2011 | 04-12-2019 |
252 | Dahej SEZ power project | Government Infrastructure Projects (PPP) | Energy | Electricity generation (grid) | Gujarat | Operation and Maintenance Stage | 5,325.39 | Not Available | 12-08-2019 | |
253 | Setting up of 500 MW Barauni thermal power unit in Begusarai district | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Bihar | Bihar State Power Generation Company Limited | Under Construction | 5,308.07 | 11-Mar-2011 | 04-12-2019 |
254 | Dr. Narla Tata Rao Coal Based Power Project - Stage V | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Andhra Pradesh | Andhra Pradesh Power Generation Corporation Limited | Under Construction | 5,287.00 | 15-Dec-2015 | 07-08-2016 |
255 | Setting up of 600 MW Kameng hydel power unit at West Kameng# | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Arunachal Pradesh | North Eastern Electric Power Corporation Limited | Under Construction | 5,269.00 | 08-Apr-2004 | 04-12-2019 |
256 | Multi-Product SEZ (Sinnar) Project | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Maharashtra | Maharashtra Industrial Development Corporation | Completed | 5,264.00 | Not Available | 09-10-2019 |
257 | Coal Based Power (Tuticorin-525 MW) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Tamil Nadu | Megha Engineering and Infrastructures Private Limited | Under Construction | 5,250.00 | 28-Feb-2016 | 31-03-2016 |
258 | Multipurpose Cargo Port (Rewas) Project # | Government Infrastructure Projects (PPP) | Transport | Ports (excluding captive) | Maharashtra | Maharashtra Maritime Board (MMB) | Pre-construction Stage | 5,200.00 | 17-Mar-2002 | 08-11-2019 |
259 | LNG Re-gasification Terminal (Mundra) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Oil/ Gas/ LNG Storage | Gujarat | GSPC LNG Limited | Under Construction | 5,200.00 | 14-Apr-2014 | 22-12-2015 |
260 | 1500 MW Bawana Power Project [Pragati-III] | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Delhi (UT) | Pragati Power Corporation Limited | Completed | 5,195.81 | Not Available | 16-12-2015 |
261 | Kochi Metro Rail Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Urban public transport (except rolling stock) | Kerala | Kochi Metro Rail Limited | Under Construction | 5,181.79 | 07-Jun-2013 | 01-07-2019 |
262 | Transmission Line (Bara-Mainpuri) Project * | Government Infrastructure Projects (PPP) | Energy | Electricity transmission | Uttar Pradesh | Uttar Pradesh Power Transmission Corporation Limited | Under Construction | 5,158.91 | 31-Jan-2012 | 01-11-2019 |
263 | Laying of 190 CKM Kurukshetra-Jind D/C line in Haryana* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Haryana | Power Grid Corporation of India Limited | Completed | 5,151.37 | 31-Jul-2014 | 25-11-2019 |
264 | LNG Terminal (Ennore) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Oil/ Gas/ LNG Storage | Tamil Nadu | Indian Oil Corporation Limited | Completed | 5,151.00 | 09-Jul-2015 | 03-12-2019 |
265 | Implementation of Bansagar irrigation scheme in Shahdol district | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Madhya Pradesh | Water Resources Department, Madhya Pradesh | Under Construction | 5,144.40 | 31-Dec-2007 | 09-11-2016 |
266 | Execution of NERPSIP Project in Assam, Manipur, Meghalaya, Mizoram, Tripura and Nagaland | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Multi State/ Centre | Power Grid Corporation of India Limited | Under Construction | 5,111.33 | 06-May-2016 | 25-10-2019 |
267 | Noida Metro Rail Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Urban public transport (except rolling stock) | Uttar Pradesh | Noida Metro Rail Corporation Limited | Under Construction | 5,103.00 | 18-Oct-2014 | 18-01-2016 |
268 | Floating Storage & Regasification Terminal (Digha) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Oil/ Gas/ LNG Storage | West Bengal | Kolkata Port Trust | Pre-construction Stage | 5,100.00 | 01-Sep-2015 | 03-10-2016 |
269 | Rihand Coal Based Power Project - Stage III | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Uttar Pradesh | NTPC Limited | Completed | 5,093.01 | 28-Jan-2009 | 01-07-2019 |
270 | Setting up a 10 MMTPA second LNG terminal at Dahej in Bharuch district * | Government Infrastructure Projects (Traditional Procurement) | Energy | Oil/ Gas/ LNG Storage | Gujarat | Petronet LNG Limited | Under Construction | 5,060.00 | 07-Jan-2014 | 26-11-2019 |