List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
1081 | Mayiladuturai-Karaikkudi & Tiruturaipundi-Agastiyampalli GC Railway Line | Government Infrastructure Projects (Traditional Procurement) | Transport | Railway track, tunnel, viaducts, bridges | Tamil Nadu | Southern Railway | Under Construction | 1,005.00 | Not Available | 25-10-2019 |
1082 | Upgradation of Jharpokharia-Baleshwar road in length of 80.6 km on NH-5. | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Odisha | National Highways Authority of India (NHAI) | Under Construction | 1,003.00 | 22-Feb-2016 | 25-10-2019 |
1083 | Karcham Wangtoo- Abdullapur Transmission Line | Government Infrastructure Projects (PPP) | Energy | Electricity transmission | Himachal Pradesh | Power Grid Corpn. of India Ltd. | Operation and Maintenance Stage | 1,003.00 | 22-Feb-2007 | 20-12-2018 |
1084 | Doubling of Surendranagar-Rajkot railway line in length of 116.2 km | Government Infrastructure Projects (Traditional Procurement) | Transport | Railway track, tunnel, viaducts, bridges | Gujarat | Western Railway | Pre-construction Stage | 1,002.39 | 01-Aug-2016 | 25-10-2019 |
1085 | Setting up of 200 MW wind based power at Thoothukudi | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Tamil Nadu | Solar Energy Corporation of India | Completed | 1,000.00 | 16-Oct-2017 | 04-12-2019 |
1086 | Fuel Fabrication Facility (Rawatbhatta) | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Rajasthan | Nuclear Fuel Complex | Completed | 1,000.00 | Not Available | 03-12-2019 |
1087 | Setting up of 100 MW solar based power unit at Gani-Sakunala Solar Park in Kurnool district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | NTPC Limited | Completed | 1,000.00 | 23-Dec-2015 | 03-12-2019 |
1088 | Solar Power (Veltoor) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Telangana | SE Solar Limited | Completed | 1,000.00 | 13-Jan-2016 | 21-11-2019 |
1089 | Integrated Border Check Post (Maharashtra) Project - Modernisation* | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Maharashtra | Maharashtra State Road Development Corporation Limited (MSRDC) | Under Construction | 1,000.00 | 05-May-2009 | 09-11-2019 |
1090 | Shipyards (Udupi) Project* | Government Infrastructure Projects (Traditional Procurement) | Transport | Ports (excluding captive) | Karnataka | Tebma Shipyards Limited | Under Construction | 1,000.00 | Not Available | 01-11-2019 |
1091 | Setting up a 100 MW Wind Power unit at Nimbagallu in Anantapur district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Tata Power Renewable Energy Limited | Pre-construction Stage | 1,000.00 | 17-Dec-2015 | 25-10-2019 |
1092 | Setting up a food park at Multi-modal International Cargo Hub and Airport in Nagpur* | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Maharashtra | Patanjali Ayurved Limited | Under Construction | 1,000.00 | 28-Oct-2016 | 25-10-2019 |
1093 | Setting up of 100 MW Solar Power Project in Anantapuram district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Tata Power Renewable Energy Limited | Under Construction | 1,000.00 | 25-Oct-2016 | 25-10-2019 |
1094 | Solar Power (Bhuj) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | RA Solar Power Private Limited | Completed | 1,000.00 | 23-Sep-2015 | 03-06-2019 |
1095 | Setting up of 100 MW solar based power unit at Pavagada solar park in Tumkuru | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Karnataka | Fortum India Private Limited | Under Construction | 1,000.00 | 05-Apr-2017 | 08-11-2017 |
1096 | Development of an IT park 'Spire Edge' - a Green Building Office Complex at Manesar in Gurgaon district | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Haryana | A N Buildwell Private Limited | Completed | 1,000.00 | 31-Dec-2008 | 31-10-2016 |
1097 | Mahindra World City (Jaipur) Project | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Rajasthan | Mahindra World City (Jaipur) Limited | Completed | 1,000.00 | 31-Oct-2005 | 03-10-2016 |
1098 | Wind Power (Shajapur-200 MW) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Inox Wind Infrastructure Services Limited | Under Construction | 1,000.00 | 31-Aug-2013 | 23-06-2016 |
1099 | Four laning of Bhavnagar-Talaja road in length of 46.5 km in Bhavnagar under NHDP-IV | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Gujarat | National Highways Authority of India (NHAI) | Operation and Maintenance Stage | 998.18 | 19-Jul-2016 | 09-11-2019 |
1100 | Setting up of 96 MW Nyukcharong Chu hydel power unit in Tawang # * | Government Infrastructure Projects (PPP) | Energy | Renewable energy (grid) | Arunachal Pradesh | Department of Hydro Power Development, Arunachal Pradesh | Pre-construction Stage | 995.90 | 21-Feb-2008 | 30-10-2019 |
1101 | Six laning of Chitradurga-Davanagere section in length of 72.7 km | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Karnataka | National Highways Authority of India (NHAI) | Operation and Maintenance Stage | 993.16 | 31-Mar-2017 | 09-11-2019 |
1102 | Water Supply Scheme (Sathupally & Wyra)* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Water supply pipeline | Telangana | Rural Water Supply and Sanitation Department, Telangana | Under Construction | 993.00 | 14-Oct-2015 | 21-11-2019 |
1103 | Two laning with paved shoulders of Raibarelly-Jaunpur Section of NH-231 from Km 0 to Km 166.4 in UP on BoT (Annuity) basis | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Uttar Pradesh | National Highways Authority of India (NHAI) | Operation and Maintenance Stage | 993.00 | 09-Nov-2012 | 19-07-2019 |
1104 | Embankments & River Protection Project (Palasbari-Gumi-Kaziranga-Dibrugarh) | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Assam | Flood and River Erosion Management Agency of Assam | Completed | 990.00 | 10-Aug-2011 | 03-12-2019 |
1105 | Four laning of Yavatmal-Wardha section in length of 64.9 km under NHDP-IV | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Maharashtra | National Highways Authority of India (NHAI) | Operation and Maintenance Stage | 988.34 | 30-Mar-2017 | 09-11-2019 |
1106 | Pandhari Irrigation Project#* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Maharashtra | Vidarbha Irrigation Development Corporation | Under Construction | 987.02 | 11-Jan-2008 | 27-11-2019 |
1107 | Setting up of 197.4 MW wind based power unit in Kachchh and Bhavnagar districts* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Torrent Power Limited | Pre-construction Stage | 987.00 | 31-Mar-2016 | 25-10-2019 |
1108 | Implementation of Upper Indravati lift irrigation scheme with a capacity of 2300 CBM* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Odisha | Water Resources Department, Odisha | Under Construction | 986.71 | 31-Mar-2014 | 25-11-2019 |
1109 | Bagalkot-Kudachi Railway Line project | Government Infrastructure Projects (Traditional Procurement) | Transport | Railway track, tunnel, viaducts, bridges | Karnataka | South Western Railway | Under Construction | 986.00 | Not Available | 25-10-2019 |
1110 | Rehabilitation, strengthening and 4 laning of Ramban to Banihal section of NH 1A in Jammu and Kashmir | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Jammu & Kashmir | Ministry of Road Transport and Highways | Under Construction | 986.00 | 15-Sep-2015 | 23-07-2019 |