List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9242 Total Project Cost(in Rs Crore): 6,813,008.32
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
811 Implementation of 220 KV gas insulated substation at Infocity-II in Bhubaneswar Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Odisha Odisha Power Transmission Corporation Limited Completed 58.12 22-Feb-2014 03-12-2019
812 Implementation of rural electrification works at Kalyan Rural - Infra Plan II - Phase A* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Maharashtra Maharashtra State Electricity Distribution Company Limited Under Construction 64.91 26-Dec-2013 03-12-2019
813 Implementation of rural electrification works in Ambernath, Badlapur & Ulhasnagar under RAPDRP-Part B* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Maharashtra Maharashtra State Electricity Distribution Company Limited Under Construction 89.61 03-Feb-2012 03-12-2019
814 Implementation of rural electrification works in Barpeta district under RGGVY XIIth Plan Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 117.71 06-Feb-2015 03-12-2019
815 Implementation of rural electrification works in Cachar district under RGGVY XIIth Plan Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 154.81 30-Jan-2015 03-12-2019
816 Implementation of rural electrification works in Darrang district under RGGVY XIIth Plan Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 86.10 12-Feb-2015 03-12-2019
817 Implementation of rural electrification works in Dhemaji district under RGGVY XIIth Plan Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 66.41 09-Feb-2015 03-12-2019
818 Implementation of rural electrification works in Dhubri district under DDUGJY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 63.97 22-Feb-2016 03-12-2019
819 Implementation of rural electrification works in Dibrugarh, Kamrup & Morigaon districts under DDUGJY* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Under Construction 57.09 26-Feb-2016 03-12-2019
820 Implementation of rural electrification works in Dima Hasao district under DDUGJY* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Under Construction 91.46 22-Feb-2016 03-12-2019
821 Implementation of rural electrification works in Hailakandi district under RGGVY XIIth Plan Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 90.78 10-Feb-2015 03-12-2019
822 Implementation of rural electrification works in Karimganj district under RGGVY XIIth Plan Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 75.27 02-Feb-2015 03-12-2019
823 Implementation of rural electrification works in Lakhimpur district under RGGVY XIIth Plan Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 84.22 16-Feb-2015 03-12-2019
824 Implementation of rural electrification works in Nagaon district under RGGVY XIIth Plan Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 110.86 21-Feb-2015 03-12-2019
825 Implementation of rural electrification works in Nuapada under RGGVY-12th Plan* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Odisha NTPC Electric Supply Company Limited Under Construction 107.86 14-Nov-2015 03-12-2019
826 Implementation of rural electrification works in Ranchi under R-APDRP Part-B scheme* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Jharkhand Jharkhand Urja Utpadan Nigam Limited Under Construction 313.85 10-Jun-2016 03-12-2019
827 Implementation of rural electrification works in Sonitpur district under RGGVY XIIth Plan Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 80.99 13-Feb-2015 03-12-2019
828 Implementation of rural electrification works in Thane under RAPDRP-Part B* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Maharashtra Maharashtra State Electricity Distribution Company Limited Under Construction 145.38 04-Jul-2013 03-12-2019
829 Implementation of rural electrification works in Tikamgarh district under DDUGJY-12th plan* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Madhya Pradesh Madhya Pradesh Poorv Kshetra Vidyut Vitaran Company Limited Under Construction 52.21 09-Sep-2014 03-12-2019
830 Integrated Power Development Scheme (Krishna, Guntur & Chittoor) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Southern Power Distribution Company of Andhra Pradesh Limited Completed 208.00 23-Dec-2015 03-12-2019
831 Inter-Regional System Strengthening Scheme [Northern & Western Region] Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Multi State/ Centre Power Grid Corporation of India Limited Completed 6,517.36 05-Feb-2015 03-12-2019
832 Laying of 280.0 CKM Barmer-Bhinmal transmission line Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Completed 95.68 22-Jan-2016 03-12-2019
833 Laying of 400 kV Jejuri-Hinjewadi DC line in Pune district - Package I* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Maharashtra Maharashtra State Electricity Transmission Company Limited Under Construction 73.03 09-Jul-2012 03-12-2019
834 Laying of 400 kV QDC BBLR- Kudus upto Naneghat line in Thane district* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Maharashtra Maharashtra State Electricity Transmission Company Limited Under Construction 371.04 04-Jun-2011 03-12-2019
835 Laying of 66 kV D/C transmission line from 66 kV switching station at Urni to Wangtoo substation* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Himachal Pradesh Himachal Pradesh Power Transmission Corporation Limited Under Construction 150.00 20-Dec-2013 03-12-2019
836 Laying of Kakching to Moreh transmission line in length of 41.1 km in Churachandpur district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Manipur Manipur State Power Company Limited Completed 53.00 12-Sep-2016 03-12-2019
837 Laying of MC & DC lines between YTPS to BTPS in length of 33.3 CKM* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Karnataka Karnataka Power Transmission Corporation Limited (KPTCL) Under Construction 99.14 09-Jul-2014 03-12-2019
838 Laying of transmission line for Gadarwara Super Thermal Power Station (STPS) - Part B in Narsimhapur district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Madhya Pradesh Power Grid Parli Transmission Limited Completed 2,360.00 29-Feb-2016 03-12-2019
839 Parichha Transmission Line Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Uttar Pradesh Power Grid Corporation of India Limited Completed 0.00 Not Available 03-12-2019
840 Rural Electrification (Bokaro) Project - DDUGJY - 12th Plan Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Jharkhand Jharkhand Bijli Vitran Nigam Limited Completed 111.24 05-Feb-2016 03-12-2019
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.