List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9242 Total Project Cost(in Rs Crore): 6,813,008.32
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
571 Setting up a 60 MW coal based power unit-1 at Bainchua Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Odisha Maadurga Thermal Power Company Limited Completed 300.00 Not Available 25-04-2017
572 Setting up a 600 MW coal based power at Butibori Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Maharashtra Vidarbha Industries Power Limited Completed 3,600.00 30-Apr-2009 25-04-2017
573 Setting up a 70 MW coal based power unit at Gummidipondi Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Tamil Nadu Tulsyan NEC Limited Completed 380.00 Not Available 25-04-2017
574 Setting up of 1050 MW Maithon Right Bank Thermal Power unit Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Jharkhand Maithon Power Limited Completed 4,450.00 28-Feb-2008 21-04-2017
575 Implementation of 120 MW coal based captive power unit at Choudwar Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Odisha Indian Metals and Ferro Alloys Limited Completed 600.00 03-Aug-2009 03-04-2017
576 Implementation of 16 MW coal based captive power unit at Sachana Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Gujarat Nirma Limited Completed 80.00 06-Sep-2012 03-04-2017
577 Implementation of 20 MW coal based captive power unit at Tatisilwai Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Jharkhand Usha Martin Limited Completed 100.00 31-Jul-2011 03-04-2017
578 Implementation of 225 MW coal based captive power unit at Makavaripalem Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Andhra Pradesh Anrak Aluminium Limited Completed 1,350.00 31-Mar-2014 03-04-2017
579 Implementation of 25 MW coal based power unit at Wajvana Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Rajasthan Trinetra Cement Limited Completed 125.00 31-Oct-2011 03-04-2017
580 Implementation of 50 MW coal based captive power unit at Wadapalli Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Telangana India Cements Limited Completed 250.00 31-May-2011 03-04-2017
581 Implementation of 50 MW coal based captive power unit in Jharsuguda Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Odisha Concast Steel and Power Limited Completed 180.00 Not Available 03-04-2017
582 Implementation of 60 MW coal based captive power unit at Mul Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Maharashtra Dhariwal Infrastructure Limited Completed 360.00 30-Sep-2010 03-04-2017
583 Implementation of 60 MW coal based power unit at Sreerampuram Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Andhra Pradesh Simhadri Power Limited Completed 315.00 Not Available 03-04-2017
584 Implementation of 80 MW of coal based power Unit-IV at Gummidipoondi Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Tamil Nadu OPG Power Generation Private Limited Completed 400.00 Not Available 03-04-2017
585 Setting up of 10 MW coal based captive power unit at Padana Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Gujarat Kutch Chemical Industries Limited Completed 60.00 18-Nov-2011 03-04-2017
586 Setting up of 1320 MW Mouda coal based power unit - Stage II in Nagpur Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Maharashtra NTPC Limited Completed 7,921.47 02-Feb-2013 03-04-2017
587 Setting up of 65 MW coal based power unit in Bilaspur Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Chhattisgarh Vandana Vidhyut Limited Completed 390.00 01-Jun-2012 03-04-2017
588 Setting up a 1050 MW coal based power plant at village Malibrahmani in Chandipada block in Angul Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Odisha Monnet Power Limited Under Construction 6,330.00 31-Jan-2008 24-03-2017
589 Setting up a 1320 MW Barh super thermal based power unit stage-II at Barh in Patna Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Bihar NTPC Limited Completed 10,071.50 31-Mar-2008 24-03-2017
590 Setting up a 1500 MW coal based power unit at Jhajjar Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Haryana Haryana Power Generation Corporation Limited Completed 10,131.00 05-Jul-2007 24-03-2017
591 Setting up of 100 MW Ratija Coal Based Power Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Chhattisgarh Spectrum Coal and Power Limited Completed 200.00 30-Dec-2008 24-03-2017
592 Setting up of 16 MW coal based captive power unit at Chintalapalem in Nalgonda Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Telangana Anjani Portland Cement Limited Completed 80.00 31-Aug-2016 24-03-2017
593 Setting up of 390 MW coal based power units (Stage-II) at Katni in Muzaffarpur Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Bihar Kanti Bijlee Utpadan Nigam Limited Completed 4,779.00 06-Mar-2010 24-03-2017
594 Setting up of 500 MW, Vindhyachal coal based power project (Unit-13) Stage-V at Vindhyanagar, Singrauli in Siddhi Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Madhya Pradesh NTPC Limited Completed 3,180.00 28-Dec-2011 24-03-2017
595 Renovation and modernisation of 1000 MW Anpara 'B' coal based power unit-4 & 5 in Sonbhadra Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Uttar Pradesh Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited Completed 691.97 30-Jul-2015 20-03-2017
596 Setting up of 1980 MW coal based power unit at Koradi in Nagpur Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Maharashtra Maharashtra State Power Generation Company Limited Completed 14,026.00 23-Sep-2009 20-03-2017
597 Neyveli Power Project I - Expansion Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Tamil Nadu NLC India Limited Completed 1,420.27 15-Jul-1999 06-03-2017
598 Neyveli Power Project II - Expansion Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Tamil Nadu NLC India Limited Completed 3,583.77 19-Aug-2005 06-03-2017
599 Setting up of 1500 MW Coal Based Power unit in Thiruvallur district Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Tamil Nadu NTPC Tamilnadu Energy Company Limited Completed 9,193.29 16-Sep-2007 06-03-2017
600 Setting up of 250 MW coal based power unit at Rourkela in Sundargarh district Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Odisha NTPC-SAIL Power Company Limited Under Construction 1,600.00 16-May-2016 06-03-2017
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.