List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
2281 Implementation of Sewerage Scheme in district 'E' of Allahabad Government Infrastructure Projects (Traditional Procurement) Water Sanitation Sewage collection, treatment and disposal system Uttar Pradesh Uttar Pradesh State Ganga River Conservation Agency Completed 142.00 05-Dec-2011 31-10-2016
2282 Implementation of Underground Sewerage Scheme of 12 MLD in Pudukkottai Municipality Government Infrastructure Projects (Traditional Procurement) Water Sanitation Sewage collection, treatment and disposal system Tamil Nadu Pudukkottai Municipality Completed 51.30 11-Feb-2008 31-10-2016
2283 Laying of 1000 Km long transmission line at Mundra in Kachchh district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Gujarat Adani Power Private Limited Completed 1,380.00 31-May-2009 31-10-2016
2284 Laying of 400 kV D/C Muzaffarpur-Susand Transmission Line in length of 87 CKM in Muzaffarpur district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Bihar IL&FS Energy Development Company Limited Completed 210.70 01-Jan-2015 31-10-2016
2285 Modernisation of 120MW Harduaganj Coal Based Power Unit 7 in Aligarh district Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Uttar Pradesh Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited Completed 231.71 31-Aug-2011 31-10-2016
2286 Setting up of 10 MW Solar Power unit at Bali in Pali district under JNNSM Phase II-Batch I Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Laxmi Diamond Private Limited Completed 70.00 28-Mar-2015 31-10-2016
2287 Setting up of 10 MW Solar Power unit at Gurha in Bikaner district under JNNSM Phase I-Batch II Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Sai Maithili Power Company Private Limited Completed 70.00 25-Jan-2012 31-10-2016
2288 Setting up of 10 MW Solar Power Unit at Kamalapuram in Tuticorin district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu TN Solar Energy Private Limited Completed 70.00 30-Apr-2015 31-10-2016
2289 Setting up of 10 MW Solar Power unit at Mangoon in Perambalur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu SEI Adityashakti Private Limited Completed 70.00 31-Dec-2014 31-10-2016
2290 Setting up of 10 MW Solar Power unit at Nimbahera in Bhilwara district under JNNSM Phase II Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan RDA Energy Private Limited Completed 70.00 25-Jan-2012 31-10-2016
2291 Setting up of 10 MW Solar Power unit at Pokaran in Jaisalmer district under JNNSM Phase II Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Palimarwar Solar Project Private Limited Completed 70.00 28-Mar-2014 31-10-2016
2292 Setting up of 140 MW Solar Power unit at Bhadla in Jodhpur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Essel Mining & Industries Limited Completed 140.00 28-Mar-2013 31-10-2016
2293 Setting up of 15 MW Wind Power unit at Kayathar in Tuticorin district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Atria Power Corporation Limited Completed 250.00 17-Nov-2015 31-10-2016
2294 Setting up of 15 MW Solar Power unit at Monjanur in Karur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Swelect Energy Systems Limited Completed 105.00 31-Jan-2013 31-10-2016
2295 Setting up of 18 MW Coal Based Power plant in Valsad district Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Gujarat Atul Limited Completed 144.00 30-Apr-2015 31-10-2016
2296 Setting up of 20 MW Solar Power unit at Bari Sid in Jodhpur district - Medha Energy Private Limied Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Medha Energy Private Limied Completed 140.00 28-Mar-2014 31-10-2016
2297 Setting up of 30 MW Solar Power unit at Kalyan Singh Ki Sid in Jodhpur district under JNNSM Phase II Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan SEI Suryalabh Private Limited Completed 210.00 25-Jan-2012 31-10-2016
2298 Setting up of 31.5 MW Solar Power unit at Mirpur Lalan in Mansa district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Punjab Bhanu Energy Infrastructure & Power Limited Completed 200.00 30-Jun-2014 31-10-2016
2299 Setting up of 4 MW Periyar Vaigai-III Small Hydro Electric Power Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Tamil Nadu Generation and Distribution Corporation Limited Completed 75.00 31-May-2011 31-10-2016
2300 Setting up of 40 MW Solar Power Unit at Moolippatti in Virudhunagar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Giriraj Enterprises Completed 250.00 31-Dec-2014 31-10-2016
2301 Setting up of 5 MW Solar Photovoltaic Power Project at Bhachau in Kachchh Distrct Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Euro Solar Power Private Limited Completed 50.00 01-Aug-2011 31-10-2016
2302 Setting up of 5 MW Solar Photovoltaic Power Project at Charanka in Patan Distrct Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat GSPC Pipavav Power Company Limited Completed 50.00 01-Dec-2011 31-10-2016
2303 Setting up of 5 MW Solar Photovoltaic Power Project at Fatepur in Surendranagar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat EMCO Limited Completed 50.00 01-Oct-2011 31-10-2016
2304 Setting up of 5 MW Solar Photovoltaic Power Project in Patan Distrct Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Jaihind Projects Limited Completed 50.00 15-Dec-2012 31-10-2016
2305 Setting up of 5 MW Solar Power Project at Shiv Lakhash in Kachchh district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Backbone Enterprises Limited Completed 70.00 02-Dec-2011 31-10-2016
2306 Setting up of 50 MW Solar Photovoltaic Power Project in Sabarkantha district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Aatash Power Private Limited Completed 500.00 15-Dec-2012 31-10-2016
2307 Setting up of 50 MW Solar Power unit at That in Jaisalmer district under JNNSM Phase II-Batch I Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Today Green Energy Private Limited Completed 350.00 28-Mar-2014 31-10-2016
2308 Setting up of 8 MW Solar Power Unit at Muthuramalingapuram in Virudhunagar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu TN Solar Energy Private Limited Completed 56.00 30-Apr-2015 31-10-2016
2309 Setting up of 9 MW Solar Photovoltaic Power Project in Kachchh Distrct Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Integrated Coal Mining Limited Completed 110.00 01-Sep-2011 31-10-2016
2310 Water Treatment Plant (Netivli Hill) Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water treatment plants Maharashtra Kalyan Dombivli Municipal Corporation Completed 106.81 02-Mar-2009 31-10-2016
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.