List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
2071 Setting up of 8.0 MW wind power unit at Balavenkatapuram in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Rayala Wind Power Company Private Limited Completed 56.70 16-Mar-2013 11-01-2017
2072 Setting up of 8.0 MW wind power unit at Kalyandurg in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Blyth Wind Park Private Limited Completed 57.00 30-Jun-2013 11-01-2017
2073 Setting up of 8.0 MW wind power unit at Nallakonda in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Vish Wind Infrastructure LLP Completed 56.00 01-Feb-2009 11-01-2017
2074 Setting up of 8.0 MW wind power unit at Nallakonda in Anantapur district - Phase V Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Khandke Wind Energy Private Limited Completed 56.00 24-Apr-2011 11-01-2017
2075 Setting up of 8.0 MW wind power unit at Nallakonda in Anantapur district - Phase VI Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Khandke Wind Energy Private Limited Completed 60.00 30-Jun-2011 11-01-2017
2076 Setting up of 8.4 MW wind power unit at Tallimadugula in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh KRBL Limited Completed 60.48 31-May-2012 11-01-2017
2077 Setting up of 8.4 MW wind power unit at Vajrakarur in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Mytrah Vayu (Pennar) Private Limited Completed 58.80 31-Dec-2009 11-01-2017
2078 Setting up of 9.6 MW wind power unit at Nallakonda in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Tadas Wind Energy Limited Completed 67.20 16-Feb-2009 11-01-2017
2079 Upgradation of various roads in length of 38.6 Km in Darbhanga district Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Bihar Road Construction Department, Bihar Completed 53.57 21-Jan-2013 11-01-2017
2080 Implementation of rural electrification works at Ballarshah, Chandrapur & Warora - Infra Plan II - Phase VI Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Maharashtra Maharashtra State Electricity Distribution Company Limited Completed 164.96 02-Mar-2009 26-12-2016
2081 Implementation of rural electrification works at Bhokar & Degalur - Infra Plan II - Phase A Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Maharashtra Maharashtra State Electricity Distribution Company Limited Completed 85.46 06-Sep-2014 26-12-2016
2082 Laying of 220 kV new Bhusawal-Chalisgaon DC line in Jalgaon district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Maharashtra Maharashtra State Electricity Transmission Company Limited Completed 53.13 27-Aug-2009 26-12-2016
2083 Laying of Anaikadavu-Rasipalayam in length of 43 km in Coimbatore district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Tamil Nadu Tamil Nadu Generation and Distribution Corporation Limited Completed 63.96 09-Oct-2013 26-12-2016
2084 Laying of Bikaner-Merta transmission line in length of 200 CKM in Bikaner district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Completed 78.00 26-Sep-2012 26-12-2016
2085 Setting up of 220 kV GIS substation at Hinjewadi in Pune district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Maharashtra Maharashtra State Electricity Transmission Company Limited Completed 106.94 20-Mar-2012 26-12-2016
2086 Setting up of 220/132 kV gas insulated substation at Vidyasagar lndustrial Park in Midnapore district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission West Bengal West Bengal State Electricity Transmission Company Limited Completed 70.42 22-Apr-2013 26-12-2016
2087 Capacity Expansion of 20 MW bagasse based power at Bahulgaon in Ahmednagar district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Gangamai Industries and Constructions Limited Completed 86.06 Not Available 20-12-2016
2088 Four-laning from Siliguri to Islampur section of 19.3 km on NH-31 (WB-7) in Darjeeling district Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal National Highways Authority of India (NHAI) Completed 225.00 31-Oct-2005 20-12-2016
2089 Gauge conversion of Kanpur-Kasganj-Mathura and Kasganj-Bareilly railway line in length of 544.5 Km Government Infrastructure Projects (Traditional Procurement) Transport Railway track, tunnel, viaducts, bridges Uttar Pradesh North Eastern Railway Completed 1,634.22 30-Nov-2001 20-12-2016
2090 Implementation of Jodhpur-Merta transmission line in length of 320 CKM Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Completed 111.95 27-Jan-2014 20-12-2016
2091 Implementation of LPG pipeline between Mangalore-Yediyur with a capacity of 3.1 MMTPA Government Infrastructure Projects (Traditional Procurement) Energy Gas pipelines Karnataka Hindustan Petroleum Corporation Limited Completed 838.08 20-Nov-2012 20-12-2016
2092 Road Upgradation of 25.1 km Ramjibanpur-Palita-Palitpur-Natunhat road in Burdwan Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Public Works Department, West Bengal Completed 68.37 21-Apr-2015 20-12-2016
2093 Setting up a 40 MWp solar photovoltaic power unit at Hardnani village in Jodhpur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Azure Green Tech Private Limited Completed 342.60 09-Apr-2014 20-12-2016
2094 Setting up of 15 MW bagasse based power unit at Shirala in Sangli district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Vishwasrao Naik SSK Limited Completed 62.00 30-Sep-2009 20-12-2016
2095 Setting up of 15 MW Karikkayam hydro electirc power project at chittar village in Pathanmthitta district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Kerala Ayyappa Hydro Power Limited Completed 146.59 03-May-2013 20-12-2016
2096 Setting up of 26 MW captive coal based power unit at Gondiparla in Kurnool district Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Andhra Pradesh Sree Rayalaseema Alkalies & Allied Chemicals Limited Completed 208.00 01-Dec-2010 20-12-2016
2097 Setting up of 5 MW of solar photovoltaic power unit at Peravali in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Narasimhaswamy Solar Generation Private Limited Completed 50.00 Not Available 20-12-2016
2098 Setting up of 50 MW wind based power unit at Bercha in Ratlam district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Orange Renewable Power Private Limited Completed 500.00 31-Jul-2015 20-12-2016
2099 Upgradation of Dehri-Nasariganj-Bikaramganj-Dinara road in length of 43 km of SH-15 Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Bihar Road Construction Department, Bihar Completed 69.65 15-Jun-2015 20-12-2016
2100 Implementation of rural electrification works at Ambejogai & Tuljapur Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Maharashtra Maharashtra State Electricity Distribution Company Limited Completed 191.00 30-Oct-2011 18-12-2016
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.