List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
1381 Setting up a 15 MW bagasse based power at Sankonatti village, Athani taluka in Belagavi Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Krishna SSK Limited Completed 97.43 28-Feb-2015 03-06-2019
1382 Setting up of 11 MW municipal solid waste based power unit in Nalgonda Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Telangana RDF Power Projects Limited Completed 100.00 23-Jun-2009 03-06-2019
1383 Setting up of 15 MW waste heat recovery based power unit at Sanghipuram in Kachchh district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Sanghi Industries Limited Completed 150.00 31-Jan-2016 03-06-2019
1384 Setting up of 25 MW solar power unit at Site No.07 in Gujarat Solar Park Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Mahindra Renewables Private Limited Completed 200.00 29-Jul-2016 03-06-2019
1385 Setting up of 50 MW solar based power unit at Yeduktla, Jayanna, Tirumalapur and Munnanur Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Telangana Mytrah Agriya Power Private Limited Completed 372.64 15-Mar-2017 03-06-2019
1386 Setting up of 50 MW solar photovoltaic power unit (Phase II) in Karnataka Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Welspun Energy Limited Completed 322.27 01-Nov-2014 03-06-2019
1387 Setting up of 50 MW solar photovoltaic power unit in Karnataka Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Welspun Energy Limited Completed 318.64 01-Nov-2014 03-06-2019
1388 Setting up of 50 MW Wind Power in Savarkundla district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Atria Power Corporation Limited Completed 500.00 11-Jul-2016 03-06-2019
1389 Setting up of 60 MW solar photovoltaic power unit at Karajagi in Solapur district. Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Enrich Energy Private Limited Completed 420.00 30-Apr-2016 03-06-2019
1390 Solar Photovoltaic Power (Bhoruka-20 MW) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Bhoruka Power Corporation Limited Completed 127.64 01-Nov-2014 03-06-2019
1391 Solar Photovoltaic Power (Sudi) Project [Phase-I] Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat KPI Global Infrastructure Limited Completed 50.00 31-Aug-2015 03-06-2019
1392 Solar Power (Bhuj) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat RA Solar Power Private Limited Completed 1,000.00 23-Sep-2015 03-06-2019
1393 Kishangarh Gulabpura NH 79 Project ROB Government Infrastructure Projects (PPP) Transport Roads and bridges Maharashtra National Highways Authority of India (NHAI) Completed 16.66 27-Nov-1998 28-01-2019
1394 Nephrology and Dialysis unit at Coronation Hospital in Dehradun Government Infrastructure Projects (PPP) Social and Commercial Infrastructure Health Care Uttarakhand Directorate of Health Services, Uttarakhand Completed 5.40 23-Feb-2010 29-11-2018
1395 Nephrology Dialysis unit at Base Hospital in Haldwani Government Infrastructure Projects (PPP) Social and Commercial Infrastructure Health Care Uttarakhand Directorate of Health Services, Uttarakhand Completed 5.40 08-Mar-2011 29-11-2018
1396 Pali Bypass (Beawar-Bar-Sirohi Road) Project Government Infrastructure Projects (PPP) Transport Roads and bridges Rajasthan Public Works Department, Rajasthan Completed 10.25 21-Nov-1996 28-11-2018
1397 Nasirabad ROB Government Infrastructure Projects (PPP) Transport Roads and bridges Maharashtra Ministry of Road Transport and Highways Completed 10.45 16-Nov-1998 22-11-2018
1398 Improvement of Manglana - Makrana road Government Infrastructure Projects (PPP) Transport Roads and bridges Rajasthan Public Works Department, Rajasthan Completed 6.54 12-Oct-2001 20-03-2018
1399 Thane Bhiwandi Bypass Government Infrastructure Projects (PPP) Transport Roads and bridges Maharashtra Ministry of Road Transport and Highways Completed 104.00 21-Sep-1998 19-03-2018
1400 Coal Based Power (Bokaro) Project - Augmentation Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Jharkhand Bokaro Power Supply Company Completed 350.00 31-Mar-2006 22-12-2017
1401 Construction of railway over bridge (ROB) on Baghi-Barbigha road of SH-83 in length of 37.6 km Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Bihar Road Construction Department, Bihar Completed 170.32 10-Oct-2013 22-12-2017
1402 Re-gasified LNG Terminal (Dabhol) Project Government Infrastructure Projects (Traditional Procurement) Energy Oil/ Gas/ LNG Storage Maharashtra Ratnagiri Gas and Power Limited Completed 3,000.00 Not Available 22-12-2017
1403 Road Upgradation (Laxmangarh-Salasar) Project Government Infrastructure Projects (PPP) Transport Roads and bridges Rajasthan Public Works Department, Rajasthan Completed 13.96 03-Jan-2012 22-12-2017
1404 Biomass Based Power (Korba) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Chhattisgarh Shanti G D Ispat and Power Private Limited Completed 70.00 Not Available 11-12-2017
1405 Upgradation of various roads in length of 122.1 km in Bijapur district Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Karnataka Public Works, Ports and Inland Water Transport Department, Karnataka Completed 56.95 19-Oct-2012 11-12-2017
1406 Raipur Durg Expressway Government Infrastructure Projects (PPP) Transport Roads and bridges Chhattisgarh National Highways Authority of India (NHAI) Completed 114.00 01-May-2003 06-12-2017
1407 Construction of bus rapid transport system in 15.5 km at Vijayawada in Krishna Government Infrastructure Projects (Traditional Procurement) Transport Urban public transport (except rolling stock) Andhra Pradesh Vijayawada Municipal Corporation Completed 152.64 31-Dec-2007 05-12-2017
1408 Construction of two lane road over bridge at Bhadul More in length of 1 km Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Public Works Department, West Bengal Completed 67.36 22-May-2012 05-12-2017
1409 Implementation of 15.5 MLD sewerage scheme in Margao town Government Infrastructure Projects (Traditional Procurement) Water Sanitation Sewage collection, treatment and disposal system Goa Sewerage & Infrastructural Development Corporation of Goa Limited Completed 208.00 30-May-2009 05-12-2017
1410 Implementation of 1600 MW Krishnapatnam coal based power unit in Nellore Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Andhra Pradesh Andhra Pradesh Power Development Company Limited Completed 8,340.00 05-Mar-2012 05-12-2017
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.