List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
1201 | Road Upgradation (Assam) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Assam | Ministry of Road Transport and Highways | Completed | 573.00 | Not Available | 02-07-2019 |
1202 | Road Upgradation (Badi-Baktara-Shahganj-Budhni) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Madhya Pradesh | Madhya Pradesh Road Development Corporation Limited (MPRDC) | Completed | 143.22 | Not Available | 02-07-2019 |
1203 | Road Upgradation (Bilaspur-Raipur) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Chhattisgarh | Public Works Department, Chhattisgarh | Completed | 79.47 | 27-Aug-2011 | 02-07-2019 |
1204 | Road Upgradation (Bishnupur-Kotulpur-Jayrambati-Kamarpukur) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | West Bengal | Public Works Department, West Bengal | Completed | 55.41 | 19-Aug-2013 | 02-07-2019 |
1205 | Road Upgradation (Damoh-Hata-Galsabad-Semariya) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Madhya Pradesh | Madhya Pradesh Road Development Corporation Limited (MPRDC) | Completed | 118.93 | 04-Jul-2011 | 02-07-2019 |
1206 | Road Upgradation (ESI Hospital-Rajeev Gandhi Nagar) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Rajasthan | Urban Improvement Trust, Kota | Completed | 68.28 | 30-Oct-2010 | 02-07-2019 |
1207 | Road Upgradation (Jhanjhapur-Darbanga) (BR-7) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Bihar | National Highways Authority of India (NHAI) | Completed | 388.23 | Not Available | 02-07-2019 |
1208 | Road Upgradation (Kangayam-Coimbatore KC-2) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Tamil Nadu | National Highways Authority of India (NHAI) | Completed | 89.00 | Not Available | 02-07-2019 |
1209 | Road Upgradation (Malkangiri-Motu) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Odisha | Public Works Department, Odisha | Completed | 62.38 | 08-Dec-2010 | 02-07-2019 |
1210 | Road Upgradation (Mudgal-Gangawathi) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Karnataka | Public Works, Ports and Inland Water Transport Department, Karnataka | Completed | 152.62 | 02-Dec-2012 | 02-07-2019 |
1211 | Road Upgradation (Pathankot-Jammu & Kashmir Border) (NS-36/J&K) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Jammu & Kashmir | National Highways Authority of India (NHAI) | Completed | 98.00 | Not Available | 02-07-2019 |
1212 | Road Upgradation (Shahapur-Shivarampur) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Karnataka | Public Works, Ports and Inland Water Transport Department, Karnataka | Completed | 62.49 | 25-Dec-2013 | 02-07-2019 |
1213 | Road Upgradation (Shikaripura-Soraba-Hosanagar) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Karnataka | Public Works, Ports and Inland Water Transport Department, Karnataka | Completed | 76.60 | 04-Mar-2014 | 02-07-2019 |
1214 | Road Upgradation (Simrahi-Kosi Eastern Bund NH-57) Project (BR-4) | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Bihar | National Highways Authority of India (NHAI) | Completed | 140.00 | Not Available | 02-07-2019 |
1215 | Road Upgradation (Uttar Pradesh) (NH 28) | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Uttar Pradesh | National Highways Authority of India (NHAI) | Completed | 259.77 | Not Available | 02-07-2019 |
1216 | Road Upgradation (Wadrafnagar-Janakpur-Balangi) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Chhattisgarh | Public Works Department, Chhattisgarh | Completed | 52.70 | 04-Jun-2010 | 02-07-2019 |
1217 | Rural Electrification (West Bengal-XI th Plan) RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Distribution Company Limited | Completed | 142.17 | 07-Feb-2009 | 02-07-2019 |
1218 | Sewerage Scheme (Belapur-Nerul) | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Maharashtra | Navi Mumbai Municipal Corporation | Completed | 104.37 | 18-Aug-2009 | 02-07-2019 |
1219 | Sewerage Scheme (Koparkhairane) | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Maharashtra | Navi Mumbai Municipal Corporation | Completed | 155.82 | 18-Aug-2009 | 02-07-2019 |
1220 | Sewerage Scheme (Thiruvananthapuram) Phase - I | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Kerala | Local Self Government Department, Kerala | Completed | 75.57 | 27-Feb-2009 | 02-07-2019 |
1221 | Shree Singaji Thermal Power Project - Stage I | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Madhya Pradesh | Madhya Pradesh Power Generating Company Limited | Completed | 7,820.00 | 12-Dec-2008 | 02-07-2019 |
1222 | Sipat Transmission Line - Stage I | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Chhattisgarh | Power Grid Corporation of India Limited | Completed | 110.00 | 03-Mar-2006 | 02-07-2019 |
1223 | Sipat-Seoni-Chhegaon-Ambazari Transmission Line | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Chhattisgarh | Power Grid Corporation of India Limited | Completed | 2,730.00 | Not Available | 02-07-2019 |
1224 | Solar Photovoltaic Power (Kadiri) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | NTPC Limited | Completed | 700.00 | 31-Aug-2015 | 02-07-2019 |
1225 | Solar Photovoltaic Power (Ramagundam) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Telangana | NTPC Limited | Completed | 66.36 | 21-Jan-2013 | 02-07-2019 |
1226 | Solar Photovoltaic Power Plant (Vadodara Branch Canal - chainage 25.60 kms to 36.80 kms) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Completed | 109.91 | 27-Jan-2014 | 02-07-2019 |
1227 | Sub-station (Khandwa) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Madhya Pradesh | Power Grid Corporation of India Limited | Completed | 110.00 | 15-Sep-2003 | 02-07-2019 |
1228 | Substation (Mansarovar) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Rajasthan | Rajasthan Rajya Vidyut Prasaran Nigam Limited | Completed | 56.64 | 10-Jan-2011 | 02-07-2019 |
1229 | Substation (Phagi) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Rajasthan | Rajasthan Rajya Vidyut Prasaran Nigam Limited | Completed | 463.36 | 11-Feb-2011 | 02-07-2019 |
1230 | Sunakhala-Ganjam NH 5 Road Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Odisha | National Highways Authority of India (NHAI) | Completed | 242.00 | 15-Oct-2009 | 02-07-2019 |