List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
31 | Construction of pedestrian skywalk at Dakshineswar temple area in Kolkata district | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | West Bengal | Kolkata Metropolitan Development Authority | Completed | 65.00 | 16-Mar-2015 | 04-12-2019 |
32 | Construction of six lane elevated road from Chalukya Circle to Hebbal Flyover in length of 6.9 Km in Bengaluru district | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Karnataka | Bangalore Development Authority (BDA) | Completed | 1,791.00 | 17-Sep-2016 | 04-12-2019 |
33 | Construction of Somanthali barrage on Nira river at Phaltan in Satara district # | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Maharashtra | Godavari Marathwada Irrigation Development Corporation Limited | Completed | 205.00 | 31-Oct-2010 | 04-12-2019 |
34 | Construction of tunnel from Gundavali to Kapurbawadi section 'A' in length of 6.8 km | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Water supply pipeline | Maharashtra | Municipal Corporation of Greater Mumbai | Completed | 1,543.20 | 07-Dec-2009 | 04-12-2019 |
35 | Construction of tunnel from Kapurbawadi to Bhandup Complex, Section 'B' in length of 8.2 km | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Water supply pipeline | Maharashtra | Municipal Corporation of Greater Mumbai | Completed | 1,488.50 | 08-Dec-2009 | 04-12-2019 |
36 | Construction of tunnel from Powai-Veravali-Ghatkopar in length of 6.6 km | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Water supply pipeline | Maharashtra | Municipal Corporation of Greater Mumbai | Completed | 181.83 | 18-Jan-2012 | 04-12-2019 |
37 | Development of Greenfield airport on 988.4 acres at Shirdi in Ahmedbagar | Government Infrastructure Projects (Traditional Procurement) | Transport | Airports | Maharashtra | Airports Authority of India (AAI) | Completed | 320.54 | 31-Jul-2010 | 04-12-2019 |
38 | Development of 100 Acres food park at Wahegaon and Dhangaon village, Pathan taluka in Aurangabad | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Maharashtra | Ministry of Food Processing Industries | Completed | 124.56 | 08-Mar-2013 | 04-12-2019 |
39 | Development of 3985 Acres special economic zone at Mangalore | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Karnataka | Mangalore Special Economic Zone Limited | Completed | 2,035.00 | 31-Dec-2010 | 04-12-2019 |
40 | Development of 500 MW Prototype Fast Breeder Reactor (PFBR) at Kalpakkam in Kancheepuram | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Tamil Nadu | Bharatiya Nabhikiya Vidyut Nigam Limited | Completed | 5,677.00 | 31-Jan-2004 | 04-12-2019 |
41 | Development of 55 acres mega food park at Bhimavaram | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Andhra Pradesh | Ministry of Food Processing Industries | Completed | 119.12 | 16-Dec-2013 | 04-12-2019 |
42 | Development of Kishangarh airport in Ajmer | Government Infrastructure Projects (Traditional Procurement) | Transport | Airports | Rajasthan | Airports Authority of India (AAI) | Completed | 181.00 | 31-Dec-2014 | 04-12-2019 |
43 | Establishment of 230/110 kV Substation at Kinnimangalam in Madurai District | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Tamil Nadu | Tamil Nadu Transmission Corporation Limited | Completed | 56.40 | 19-Aug-2014 | 04-12-2019 |
44 | Establishment of 400/230-110 kV substation at Sholinganallur in Kancheepuram district | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Tamil Nadu | Tamil Nadu Generation and Distribution Corporation Limited | Completed | 122.21 | 19-Mar-2014 | 04-12-2019 |
45 | Execution of common system with Costal Energen Pvt Ltd & Ind-Barath Power Ltd (LTOA) Generation Project in Tuticorin-B | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Multi State/ Centre | Power Grid Corporation of India Limited | Completed | 2,281.56 | 30-Sep-2011 | 04-12-2019 |
46 | Execution of Eastern Region Strengthening Scheme-V | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Multi State/ Centre | Power Grid Corporation of India Limited | Completed | 1,364.52 | 31-Oct-2013 | 04-12-2019 |
47 | Execution of Southern Region System Strengthening scheme - XXIV in Tamil Nadu & Andhra Pradesh | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Multi State/ Centre | Power Grid Corporation of India Limited | Completed | 1,455.47 | 15-Mar-2016 | 04-12-2019 |
48 | Execution of substation works associated with Maheshwaram Pooling Station in Telangana * | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Telangana | Power Grid Corporation of India Limited | Completed | 550.06 | 31-Mar-2015 | 04-12-2019 |
49 | Execution of transmission system associated with IPPs of Nagapattinam & Cuddalore Area - Package A in Tamil Nadu | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Tamil Nadu | Power Grid Corporation of India Limited | Completed | 1,025.00 | 16-May-2014 | 04-12-2019 |
50 | Execution of transmission system associated with Mauda Stage-II (2x660MW) Generation Projects | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Multi State/ Centre | Power Grid Corporation of India Limited | Completed | 1,575.30 | 30-Sep-2013 | 04-12-2019 |
51 | Execution of transmission system associated with Solapur STPP (2x660MW) Generation Projects-Part A | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Maharashtra | Power Grid Corporation of India Limited | Completed | 63.32 | 30-Oct-2013 | 04-12-2019 |
52 | Execution of transmission system for ultra mega solar park in Tumkur - Phase I | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Multi State/ Centre | Power Grid Corporation of India Limited | Completed | 810.48 | 30-Apr-2016 | 04-12-2019 |
53 | Execution of transmission system in North/West part of Western Region for IPP Generation Projects in Chhattisgarh-E | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Multi State/ Centre | Power Grid Corporation of India Limited | Completed | 1,822.73 | 31-Dec-2011 | 04-12-2019 |
54 | Flyover & Rail Over Bridge (Vallarpadam) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Kerala | Cochin Port Trust | Completed | 59.97 | 17-Jan-2015 | 04-12-2019 |
55 | Flyover (Amroli Junction-Mansarovar Junction) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Gujarat | Surat Municipal Corporation | Completed | 74.62 | 03-Sep-2015 | 04-12-2019 |
56 | Flyover (Bikram Chowk) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Jammu & Kashmir | Jammu and Kashmir Economic Reconstruction Agency | Completed | 71.85 | 15-May-2013 | 04-12-2019 |
57 | Flyover (Palarivattom) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Kerala | Roads and Bridges Development Corporation of Kerala Limited | Completed | 72.20 | Not Available | 04-12-2019 |
58 | Flyover (Parama-Park Circus) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | West Bengal | Kolkata Metropolitan Development Authority | Completed | 291.66 | 22-Jan-2009 | 04-12-2019 |
59 | Flyover (Patna) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Bihar | Bihar Rajya Pul Nirman Nigam Limited | Completed | 167.85 | 28-Jun-2013 | 04-12-2019 |
60 | Four laning of Dhavali bypass in length of 4 km on NH-17B | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Goa | Public Works Department, Goa | Completed | 61.38 | 02-Apr-2015 | 04-12-2019 |