List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
181 | Implementation of rural electrification works in North 24 Pargana under Integrated Power Development Scheme* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Distribution Company Limited | Under Construction | 497.38 | 25-Aug-2016 | 22-11-2019 |
182 | Implementation of rural electrification works in Purba Medinipur under Integrated Power Development Scheme* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Distribution Company Limited | Under Construction | 83.88 | 25-Aug-2016 | 22-11-2019 |
183 | Implementation of rural electrification works in Purulia & Jalpaiguri under Integrated Power Development Scheme* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Distribution Company Limited | Under Construction | 75.91 | 25-Aug-2016 | 22-11-2019 |
184 | Implementation of rural electrification works in Raiganj under Integrated Power Development Scheme* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Distribution Company Limited | Under Construction | 100.50 | 28-Feb-2017 | 22-11-2019 |
185 | Implementation of sewerage scheme at Beghore Khal and Joka Tram Depot in Kolkata district* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | West Bengal | Kolkata Municipal Corporation | Under Construction | 119.97 | 27-Oct-2014 | 22-11-2019 |
186 | Implementation of sewerage scheme at Rajabagan & Santoshpur in Kolkata* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | West Bengal | Kolkata Municipal Corporation | Under Construction | 907.00 | 05-Jan-2016 | 22-11-2019 |
187 | Setting up of 220 kV gas insulated substation at Gazol* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 93.17 | 30-Dec-2016 | 22-11-2019 |
188 | Setting up of 220 kV substation at Rejinagar* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 97.01 | 23-Dec-2016 | 22-11-2019 |
189 | Setting up of 220/132 kV substation at Barasat in North 24 Parganas district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 70.81 | 30-Aug-2016 | 22-11-2019 |
190 | Setting up of 220/132/33 kV substation at New Town II C in North 24 Parganas district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 98.92 | 14-Sep-2016 | 22-11-2019 |
191 | 8 MW Waste Based Power (Haripal) Project* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | West Bengal | Himadri Chemicals and Industries Limited | Completed | 80.00 | Not Available | 21-11-2019 |
192 | Implementation of sewerage scheme at Prantik Phase-III in Kolkata* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | West Bengal | Kolkata Municipal Corporation | Under Construction | 108.30 | 26-Oct-2016 | 21-11-2019 |
193 | Renovation of Kolaghat coal based power unit with a capacity of 630 MW - Stage I* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | West Bengal | West Bengal Power Development Corporation Limited | Under Construction | 5,040.00 | 23-Mar-2017 | 21-11-2019 |
194 | Setting up of 10 MW biomass based power unit in Birbhum district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | West Bengal | Techno Electric & Engineering Company Limited | Completed | 50.00 | 30-Aug-2011 | 21-11-2019 |
195 | Setting up of 10 MW solar photovoltaic power unit in Sagardighi* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | West Bengal | West Bengal Power Development Corporation Limited | Under Construction | 57.00 | 12-Apr-2017 | 21-11-2019 |
196 | Setting up of 10 MW waste heat recovery power unit at Gokulpur in Midnapore district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | West Bengal | Tata Metaliks Limited | Under Construction | 50.00 | 10-Aug-2016 | 21-11-2019 |
197 | Setting up of 5.5 MW solar power unit at Salboni in Paschim Medinipur district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | West Bengal | OCL India Limited | Completed | 55.00 | 30-Oct-2015 | 21-11-2019 |
198 | Solar Photovoltaic Power (Durgapur) Project* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | West Bengal | Solitaire Industrial Infrastructure Private Limited | Completed | 50.00 | Not Available | 21-11-2019 |
199 | Water Supply Project (Uluberia) Phase-II* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Water supply pipeline | West Bengal | Kolkata Metropolitan Water and Sanitation Authority | Under Construction | 124.78 | 29-Aug-2011 | 21-11-2019 |
200 | Container Terminal at Diamond Harbour (Kolkata Port) * | Government Infrastructure Projects (PPP) | Transport | Ports (excluding captive) | West Bengal | Kolkata Port Trust | Not Available | 705.88 | Not Available | 09-11-2019 |
201 | Four laning of Barasat-Krishnagar section of NH 34 in West Bengal under NHDP Phase III on BOT (Annuity) basis* | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | West Bengal | National Highways Authority of India (NHAI) | Under Construction | 886.73 | 20-Jun-2011 | 09-11-2019 |
202 | Four laning of Farakka-Raiganj section of NH 34 from km 295 to km 398 inWest Bengal on DBFOT basis unde+B218r NHDP III | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | West Bengal | National Highways Authority of India (NHAI) | Operation and Maintenance Stage | 1,056.56 | 19-Jul-2010 | 09-11-2019 |
203 | Four laning of Krishnanagar-Baharampur section of NH 34 from Km 115 to km 193 in the State of West Bengal +B235 | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | West Bengal | National Highways Authority of India (NHAI) | Operation and Maintenance Stage | 708.26 | 06-Jun-2011 | 09-11-2019 |
204 | Road Upgradation (Jinzira Bazzar-Batanagar) Project | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | West Bengal | Kolkata Metropolitan Development Authority | Operation and Maintenance Stage | 24.30 | 28-May-2014 | 09-11-2019 |
205 | Six laning of Dhankuni-Kharagpur section in length of 111.4 km on NH-6 under NHDP-V | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | West Bengal | National Highways Authority of India (NHAI) | Operation and Maintenance Stage | 1,396.20 | 20-Jun-2011 | 09-11-2019 |
206 | Solid Waste Management (700 TPD) at Asansol UA * | Government Infrastructure Projects (PPP) | Water Sanitation | Solid waste management | West Bengal | Asansol Durgapur Development Authority | Under Construction | 44.00 | 23-Dec-2008 | 09-11-2019 |
207 | Development of a multipurpose Berth and a Mechanised Berth at Haldia Dock -II (North), Haldia Dock Complex, Kolkata Port Trust * | Government Infrastructure Projects (PPP) | Transport | Ports (excluding captive) | West Bengal | Ministry of Shipping | Under Construction | 821.40 | 14-Jun-2014 | 08-11-2019 |
208 | Office cum Institutional cum Commercial Complex at Salt Lake * | Government Infrastructure Projects (PPP) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | West Bengal | Kolkata Metropolitan Development Authority | Under Construction | 500.00 | 06-Mar-2008 | 08-11-2019 |
209 | Riverine Multipurpose Jetty at Haldia Port * | Government Infrastructure Projects (PPP) | Transport | Ports (excluding captive) | West Bengal | Kolkata Port Trust | Pre-construction Stage | 278.90 | Not Available | 08-11-2019 |
210 | Construction of sewerage network in length of 11.6 km at Rania in South 24 Parganas district* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | West Bengal | Kolkata Municipal Corporation | Under Construction | 76.03 | 17-Oct-2016 | 05-11-2019 |