List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
541 | Sarju Hydel Power Project - Stage II | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Completed | 91.49 | Not Available | 22-07-2019 |
542 | Sarju Hydel Power Project - Stage III | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Completed | 65.80 | Not Available | 22-07-2019 |
543 | Four laning of Rampur-Kathgodam section of NH-87 from km 0 to km 88 in UP and Uttarakhand on BoT (Toll) basis | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Uttarakhand | National Highways Authority of India (NHAI) | Under Construction | 790.00 | 02-Jun-2016 | 19-07-2019 |
544 | Bridge (Dobra-Chanthi) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Uttarakhand | Public Works Department, Uttarakhand | Under Construction | 150.00 | 25-Jan-2015 | 02-07-2019 |
545 | Bhilangana Hydro Power Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | Uttarakhand Renewable Energy Development Agency | Completed | 176.43 | 02-Aug-2013 | 10-06-2019 |
546 | 225 MW combined cylce gas turbine power project in Uttarakhand | Government Infrastructure Projects (PPP) | Energy | Electricity generation (grid) | Uttarakhand | Operation and Maintenance Stage | 1,380.00 | Not Available | 17-12-2018 | |
547 | Implementation of 237 TPD solid waste management system at Haridwar | Government Infrastructure Projects (PPP) | Water Sanitation | Solid waste management | Uttarakhand | Nagar Nigam Haridwar | Operation and Maintenance Stage | 18.56 | 22-Oct-2012 | 17-12-2018 |
548 | Nephrology and Dialysis unit at Coronation Hospital in Dehradun | Government Infrastructure Projects (PPP) | Social and Commercial Infrastructure | Health Care | Uttarakhand | Directorate of Health Services, Uttarakhand | Completed | 5.40 | 23-Feb-2010 | 29-11-2018 |
549 | Nephrology Dialysis unit at Base Hospital in Haldwani | Government Infrastructure Projects (PPP) | Social and Commercial Infrastructure | Health Care | Uttarakhand | Directorate of Health Services, Uttarakhand | Completed | 5.40 | 08-Mar-2011 | 29-11-2018 |
550 | Cardiac Care Unit at Coronational Hospital in Dehradun | Government Infrastructure Projects (PPP) | Social and Commercial Infrastructure | Health Care | Uttarakhand | Directorate of Health Services, Uttarakhand | Operation and Maintenance Stage | 17.67 | 08-Mar-2011 | 28-11-2018 |
551 | Setting up of food park on 50 acres at Kashipur | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Uttarakhand | Ministry of Food Processing Industries | Completed | 100.00 | 23-Jan-2014 | 19-07-2017 |
552 | Upgradation of Purkazi-Laksar-Haridwar road in length of 46.5 km | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Uttarakhand | Public Works Department, Uttarakhand | Completed | 62.76 | 21-May-2015 | 15-05-2017 |
553 | Upgradation of various roads in length of 55 km in Dehradun | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Uttarakhand | Public Works Department, Uttarakhand | Completed | 51.39 | 19-Mar-2013 | 15-05-2017 |
554 | Upgradation of various roads in length of 82.6 km at Haldwani | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Uttarakhand | Public Works Department, Uttarakhand | Completed | 51.89 | 25-Mar-2015 | 15-05-2017 |
555 | Bhilangana II A hydro project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Under Construction | 233.81 | 18-Sep-2012 | 06-03-2017 |
556 | Hydel Power (Madmaheshwar) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Under Construction | 194.52 | 01-Dec-2015 | 06-03-2017 |
557 | Hydel Power Project (Bgyunder Ganga) | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Under Construction | 137.69 | Not Available | 06-03-2017 |
558 | Hydel Power Project (Jhala Koti) | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Under Construction | 80.57 | Not Available | 06-03-2017 |
559 | Hydel Power Project (Srinagar) | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Completed | 4,192.00 | Not Available | 06-03-2017 |
560 | Kaliganga-II Small Hydro Power Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Under Construction | 65.94 | 18-Nov-2015 | 06-03-2017 |
561 | Tehri Transmission Line (Phase II) | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Uttarakhand | Power Grid Corporation of India Limited | Completed | 914.00 | Not Available | 06-03-2017 |
562 | Implementation of 220 kV substation at Baram | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Uttarakhand | Power Transmission Corporation of Uttarakhand Limited | Under Construction | 120.84 | 31-Dec-2015 | 12-01-2017 |
563 | Laying of Srinagar-Satpulli transmission line in length of 52.4 CKM | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Uttarakhand | Power Transmission Corporation of Uttarakhand Limited | Completed | 55.33 | 16-Aug-2004 | 12-01-2017 |
564 | Upgradation of Dhumakot-Nainidanda, Soparkhal-Lalitpur & Rikhanikhal-Thailisain road in 59.5 Km in Pauri Garhwal district | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Uttarakhand | Public Works Department, Uttarakhand | Completed | 69.10 | 30-Jan-2010 | 05-12-2016 |
565 | Upgradation of roads in Pauri Garhwal district in length of 48.2 Km | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Uttarakhand | Public Works Department, Uttarakhand | Completed | 61.50 | 31-Jan-2010 | 05-12-2016 |
566 | Renovation of existing 20.4 MW Pathri hydel power project in Haridwar district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Completed | 113.25 | 09-Mar-2010 | 09-11-2016 |
567 | Combined Cycle Gas Based Power (Nand Nagar Industrial Area) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Uttarakhand | Beta Infratech Private Limited | Completed | 845.96 | 30-May-2011 | 03-10-2016 |
568 | Warehouses (Pantnagar) Project | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Uttarakhand | Container Corporation of India Limited | Completed | 120.00 | 28-Jan-2014 | 03-10-2016 |
569 | Transmission Line (Rudrapur-Srinagar) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Uttarakhand | Power Transmission Corporation of Uttarakhand Limited | Under Construction | 124.00 | 31-Aug-2015 | 14-09-2016 |
570 | Tehri Pumped Storage Plant (1000 MW) | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | THDC India Limited | Completed | 2,978.86 | 27-Jul-2011 | 04-05-2016 |