List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
1561 | Setting up of 15 MW solar power unit at Ramannapet village in Nalgonda district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Telangana | Avighna Solar Farms Limited | Pre-construction Stage | 120.00 | 29-Feb-2016 | 25-10-2019 |
1562 | Setting up of 18 MW Dengzi hydel power unit at Kalaktang # * | Government Infrastructure Projects (PPP) | Energy | Renewable energy (grid) | Arunachal Pradesh | Department of Hydro Power Development, Arunachal Pradesh | Pre-construction Stage | 133.20 | 25-Nov-2015 | 25-10-2019 |
1563 | Setting up of 197.4 MW wind based power unit in Kachchh and Bhavnagar districts* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Torrent Power Limited | Pre-construction Stage | 987.00 | 31-Mar-2016 | 25-10-2019 |
1564 | Setting up of 20 MW solar based power unit at Jambalapuram in Madurai district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Tamil Nadu | Bee Solar Energy Private Limited | Pre-construction Stage | 130.00 | 01-Apr-2016 | 25-10-2019 |
1565 | Setting up of 20 MW wind based power unit at Alankarayani Peta* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Synefra Engineering & Construction Limited | Under Construction | 140.00 | 30-Apr-2016 | 25-10-2019 |
1566 | Setting up of 2000 MW Upper Subansiri hydel power unit at Menga village * | Government Infrastructure Projects (PPP) | Energy | Renewable energy (grid) | Arunachal Pradesh | Department of Hydro Power Development, Arunachal Pradesh | Pre-construction Stage | 16,100.00 | 18-Mar-2010 | 25-10-2019 |
1567 | Setting up of 220 kV Vaghchipa (new) substation* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Gujarat | Power Grid Corporation of India Limited | Pre-construction Stage | 57.51 | 28-Jul-2017 | 25-10-2019 |
1568 | Setting up of 220/66/33 kV GIS substation at R K Puram in Delhi* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Delhi (UT) | Delhi Transco Limited | Pre-construction Stage | 105.24 | 10-Feb-2017 | 25-10-2019 |
1569 | Setting up of 226.8 MW wind power unit at Amidala in Anantapur district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Skeiron Renewable Energy Amidyala Limited | Under Construction | 1,820.00 | 04-Aug-2016 | 25-10-2019 |
1570 | Setting up of 250 MW lignite based thermal power unit in Bikaner district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Rajasthan | NLC India Limited | Pre-construction Stage | 2,635.04 | 21-Nov-2016 | 25-10-2019 |
1571 | Setting up of 279 MW captive power plant at Dahej in Bharuch district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Gujarat | Reliance Industries Limited | Under Construction | 1,674.00 | 23-Nov-2016 | 25-10-2019 |
1572 | Setting up of 28 MW bagasse based power unit at Devrai in Bid district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Maharashtra | Shree Shambhu Mahadeo Sugar & Allied Industries Limited | Pre-construction Stage | 128.00 | 31-Dec-2015 | 25-10-2019 |
1573 | Setting up of 300 MW coal based power unit at Nardana in Dhule district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Maharashtra | Shirpur Power Private Limited | Under Construction | 2,413.00 | Not Available | 25-10-2019 |
1574 | Setting up of 31 MW Rebby hydel power unit in Kameng # * | Government Infrastructure Projects (PPP) | Energy | Electricity transmission | Arunachal Pradesh | Department of Hydro Power Development, Arunachal Pradesh | Pre-construction Stage | 217.00 | 19-Nov-2008 | 25-10-2019 |
1575 | Setting up of 36 MW Tarang Warang hydel power unit in Kameng # * | Government Infrastructure Projects (PPP) | Energy | Electricity transmission | Arunachal Pradesh | Department of Hydro Power Development, Arunachal Pradesh | Pre-construction Stage | 252.00 | 25-Oct-2007 | 25-10-2019 |
1576 | Setting up of 372 MW captive power plant at Hazira in Surat district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Gujarat | Reliance Industries Limited | Under Construction | 2,232.00 | 23-Nov-2016 | 25-10-2019 |
1577 | Setting up of 40 MW Wind Power unit at Molagavalli in Kurnool district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | KCT Renewable Energy Private Limited | Pre-construction Stage | 200.00 | 11-Aug-2016 | 25-10-2019 |
1578 | Setting up of 40 MW Wind Power unit at Ron in Gadag district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Karnataka | ReNew Power Private Limited | Pre-construction Stage | 200.00 | 19-Apr-2016 | 25-10-2019 |
1579 | Setting up of 400 MW Mihumdon hydel power unit in Arunachal Pradesh * | Government Infrastructure Projects (PPP) | Energy | Renewable energy (grid) | Arunachal Pradesh | Department of Hydro Power Development, Arunachal Pradesh | Pre-construction Stage | 2,800.00 | 02-Mar-2009 | 25-10-2019 |
1580 | Setting up of 400/220 kV substation in NCT of Delhi during 12th Plan Period-Part B1 | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Delhi (UT) | Power Grid Corporation of India Limited | Completed | 780.33 | 31-May-2015 | 25-10-2019 |
1581 | Setting up of 41 MW Lachung hydel power unit in Kameng # * | Government Infrastructure Projects (PPP) | Energy | Electricity transmission | Arunachal Pradesh | Department of Hydro Power Development, Arunachal Pradesh | Pre-construction Stage | 287.00 | 19-Nov-2008 | 25-10-2019 |
1582 | Setting up of 43.5 MW wind power unit in Anantapur district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Orient Green Power Limited | Under Construction | 286.00 | 31-Mar-2016 | 25-10-2019 |
1583 | Setting up of 45 MW Phanchung hydel power unit in Kameng # * | Government Infrastructure Projects (PPP) | Energy | Electricity transmission | Arunachal Pradesh | Department of Hydro Power Development, Arunachal Pradesh | Pre-construction Stage | 415.00 | 25-Oct-2007 | 25-10-2019 |
1584 | Setting up of 48.3 MW wind based power unit in Jaisalmer and Jodhpur districts* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Rajasthan | Indian Oil Corporation Limited | Pre-construction Stage | 241.50 | 30-Mar-2016 | 25-10-2019 |
1585 | Setting up of 50 MW solar based power unit at Wanaparthy village in Mahaboob Nagar district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Telangana | Prathamesh Solar Farms Private Limited | Pre-construction Stage | 400.00 | 29-Feb-2016 | 25-10-2019 |
1586 | Setting up of 50 MW solar photovoltaic based power unit at Teni & Dindigul | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Tamil Nadu | NHPC Limited | Completed | 400.00 | 19-Jun-2017 | 25-10-2019 |
1587 | Setting up of 50 MW wind power unit in Gujarat* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | SJVN Limited | Pre-construction Stage | 100.00 | 06-Dec-2016 | 25-10-2019 |
1588 | Setting up of 52 MW Par hydel power unit in Papum Pare # * | Government Infrastructure Projects (PPP) | Energy | Renewable energy (grid) | Arunachal Pradesh | Department of Hydro Power Development, Arunachal Pradesh | Pre-construction Stage | 461.00 | 26-Dec-2007 | 25-10-2019 |
1589 | Setting up of 60 MW New Melling hydel power unit in Tawang # * | Government Infrastructure Projects (PPP) | Energy | Renewable energy (grid) | Arunachal Pradesh | Department of Hydro Power Development, Arunachal Pradesh | Pre-construction Stage | 1,086.00 | 02-Mar-2009 | 25-10-2019 |
1590 | Setting up of 63 MW Turu hydel power unit in Papum Pare# * | Government Infrastructure Projects (PPP) | Energy | Renewable energy (grid) | Arunachal Pradesh | Department of Hydro Power Development, Arunachal Pradesh | Pre-construction Stage | 630.00 | 21-Jun-2007 | 25-10-2019 |