This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
1381 Setting up of 24.6 MW Wanger-Homte hydel power unit in Kinnaur district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 274.50 18-Oct-2006 30-10-2019
1382 Setting up of 240 MW Heo hydel power unit in West Siang # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 1,680.00 30-Jun-2007 30-10-2019
1383 Setting up of 25 MW Adum Panyor hydel power unit on Ranganadi River in Arunachal Pradesh # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 175.00 04-Feb-2010 30-10-2019
1384 Setting up of 25 MW Lambadug hydel power unit in Kangra district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 149.81 13-Jun-2002 30-10-2019
1385 Setting up of 252 MW Dinchang hydel power unit near Bomdila in West Kameng district # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 1,980.00 11-Sep-2007 30-10-2019
1386 Setting up of 27.5 MW Tagurshit-II hydel power unit in West Siang # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 192.50 11-Aug-2009 30-10-2019
1387 Setting up of 270 MW hydel power unit in Anjaw * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 1,890.00 09-Jul-2007 30-10-2019
1388 Setting up of 2700 MW Lower Siang hydel power unit in East Siang # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 20,000.00 22-Feb-2006 30-10-2019
1389 Setting up of 275 MW Emra-I hydel power unit in Arunachal Pradesh # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 1,925.00 02-Feb-2008 30-10-2019
1390 Setting up of 30 MW Ashupani hydel power unit in Arunachal Pradesh # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 210.00 08-Aug-2013 30-10-2019
1391 Setting up of 3097 MW Etalin hydel power unit in Dibang Valley district # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 25,296.95 01-Dec-2008 30-10-2019
1392 Setting up of 360 MW Nalo hydel power unit in Upper Subansiri # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 2,520.00 16-Nov-2010 30-10-2019
1393 Setting up of 38 MW Meyong hydel power unit in Kameng basin # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 266.00 15-Nov-2010 30-10-2019
1394 Setting up of 390 MW Emra-II hydel power unit in Arunachal Pradesh * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 2,730.00 02-Feb-2008 30-10-2019
1395 Setting up of 40 MW Pakke Bung-I hydel power unit in Arunachal Pradesh # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 280.00 12-Jan-2008 30-10-2019
1396 Setting up of 40 MW Rapum hydel power unit in West Siang # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 280.00 27-Dec-2007 30-10-2019
1397 Setting up of 420 MW Amulin hydel power unit in Anini district # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 2,940.00 02-Mar-2009 30-10-2019
1398 Setting up of 45 MW Lower Pachuk-II hydel power unit in Kameng # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 315.00 27-Aug-2010 30-10-2019
1399 Setting up of 45 MW Tirap hydel power unit in Changlang # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 315.00 16-Apr-2013 30-10-2019
1400 Setting up of 46 MW Digin hydel power unit in West Kameng # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 322.00 15-Nov-2010 30-10-2019
1401 Setting up of 46 MW Sepia hydel power unit in Arunachal Pradesh # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 322.00 25-Oct-2007 30-10-2019
1402 Setting up of 48 MW Ithun-II hydel power unit in Lower Dibang Valley # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 336.00 29-Nov-2008 30-10-2019
1403 Setting up of 48 MW Lower Marjingla hydel power unit in East Kameng # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 336.00 27-Aug-2010 30-10-2019
1404 Setting up of 48 MW Papu Valley hydel power unit in East Kameng # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 345.60 25-Nov-2008 30-10-2019
1405 Setting up of 5.4 MW Sarbari-II small hydel power unit in Kullu district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 46.00 15-Mar-2001 30-10-2019
1406 Setting up of 50 MW Tsa Chu-ILower hydel power unit in Tawang # * Government Infrastructure Projects (PPP) Energy Electricity transmission Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 350.00 27-Aug-2010 30-10-2019
1407 Setting up of 500 MW Emini hydel power unit in Dibang Valley district # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 3,500.00 02-Mar-2009 30-10-2019
1408 Setting up of 55 MW Para hydel power unit in Kameng # * Government Infrastructure Projects (PPP) Energy Electricity transmission Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 385.00 19-Nov-2008 30-10-2019
1409 Setting up of 552 MW Dengser hydel power unit in Upper Subansiri # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 3,864.00 26-Apr-2011 30-10-2019
1410 Setting up of 56 MW Taiyong hydel power unit in West Siang # * Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Arunachal Pradesh Department of Hydro Power Development, Arunachal Pradesh Pre-construction Stage 392.00 06-Jun-2011 30-10-2019
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.