List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
781 Bajna Wind Power Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Gamesa Wind Turbines Private Limited Under Construction 560.00 29-Oct-2014 21-11-2019
782 Bhyundar Ganga Hydro Electric Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Uttarakhand Super Hydro Private Limited Under Construction 273.00 01-Dec-2006 21-11-2019
783 Biomass Based Power (Jhabua) Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Jabua Green Power Private Limited Under Construction 50.00 Not Available 21-11-2019
784 Biomass Based Power (Perundurai) Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Perundurai Green Energy Private Limited Under Construction 57.00 09-Nov-2012 21-11-2019
785 Biomass Power (Mathura) Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Uttar Pradesh Usher Eco Power Limited Completed 81.86 Not Available 21-11-2019
786 Captive Power (Manali) Project - Expansion* Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Tamil Nadu Chennai Petroleum Corporation Limited Under Construction 158.00 Not Available 21-11-2019
787 Choramba Biomass Power Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Vidarbha Energy and Infrastructure Private Limited Under Construction 71.00 Not Available 21-11-2019
788 Co-generation Power (Chilwaria) Project - Expansion* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Uttar Pradesh Simbhaoli Sugars Limited Completed 330.00 Not Available 21-11-2019
789 Co-generation Power (Dnyaneshwarnagar) Project - Expansion* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shri Dnyaneshwar SSK Limited Under Construction 100.00 01-Feb-2016 21-11-2019
790 Development of City Gas Distribution Network at 40700 locations in Ernakulam* Government Infrastructure Projects (Traditional Procurement) Energy Gas pipelines Kerala Kerala GAIL Gas Limited Under Construction 435.00 04-Jan-2015 21-11-2019
791 Eastern Region Strengthening Scheme-I* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Multi State/ Centre Power Grid Corporation of India Limited Completed 197.00 Not Available 21-11-2019
792 Execution of 33/11 kV substations in Bilaspur & Durg districts under DDUGJY* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Chhattisgarh Chhattisgarh State Power Distribution Company Limited Under Construction 296.00 11-Nov-2016 21-11-2019
793 Expansion of bagasse based power unit from 3 MW to 30 MW at Chandrapuri in Solapur district* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shetkari Sakhar Karkhana (Chandrapuri) Limited Under Construction 120.00 01-Nov-2016 21-11-2019
794 Feeder Separation Project (Barwah & Madleshwar)* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Madhya Pradesh Madhya Pradesh Paschim Kshetra Vidyut Vitaran Company Limited Under Construction 57.74 30-Nov-2010 21-11-2019
795 Feeder Separation Project (Khandwa I & II)* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Madhya Pradesh Madhya Pradesh Paschim Kshetra Vidyut Vitaran Company Limited Under Construction 55.42 30-Nov-2010 21-11-2019
796 Feeder Separation Scheme (Bhind)* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Madhya Pradesh Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited Under Construction 82.82 20-Aug-2011 21-11-2019
797 Feeder Separation Scheme (Hoshagabad)* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Madhya Pradesh Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited Under Construction 55.19 24-Mar-2014 21-11-2019
798 Feeder Separation Scheme (Raisen) Phase 2* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Madhya Pradesh Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited Under Construction 93.76 15-Mar-2014 21-11-2019
799 Feeder Separation Scheme (Rajgarh-II)* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Madhya Pradesh Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited Under Construction 57.49 20-Aug-2011 21-11-2019
800 Feeder Separation Scheme (Vidisha)* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Madhya Pradesh Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited Under Construction 80.90 25-Jan-2011 21-11-2019
801 Gandhar Gas Power Project - Renovation* Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Gujarat NTPC Limited Under Construction 0.00 16-May-2012 21-11-2019
802 Hatod Wind Power Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Gamesa Wind Turbines Private Limited Under Construction 700.00 08-Dec-2015 21-11-2019
803 Hydro Electric Power (Saryu) Project - Stage II* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Uttarakhand Uttar Bharat Hydro Power Private Limited Completed 70.20 Not Available 21-11-2019
804 Hydro Electric Power (Saryu) Project - Stage III* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Uttarakhand Uttar Bharat Hydro Power Private Limited Completed 68.25 Not Available 21-11-2019
805 Implementaion of 400 kV substation at Doni* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Karnataka Karnataka Power Transmission Corporation Limited (KPTCL) Under Construction 176.38 30-Jul-2016 21-11-2019
806 Implementation of 132 kV substation at Pedawaltair* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 77.51 26-Feb-2013 21-11-2019
807 Implementation of 220 kV substation at Magadi* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Karnataka Karnataka Power Transmission Corporation Limited (KPTCL) Under Construction 86.67 15-May-2015 21-11-2019
808 Implementation of 220 kV substation at Pavagada* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Karnataka Karnataka Power Transmission Corporation Limited (KPTCL) Under Construction 76.61 16-Jan-2013 21-11-2019
809 Implementation of 33 kV integrated power development scheme at Bargarh under DDUGJY* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Odisha Western Electricity Supply Company of Orissa Limited Under Construction 186.64 20-Sep-2016 21-11-2019
810 Implementation of 33 kV rural electrification works in Dhamtari & Balodabazar districts under DDUGJY* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Chhattisgarh Chhattisgarh State Power Distribution Company Limited Under Construction 59.75 19-Oct-2016 21-11-2019
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.