List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
2131 Construction of multi chamber cold storage with a capacity of 4000 MT in Barmer# Government Infrastructure Projects (PPP) Social and Commercial Infrastructure Cold Chain Rajasthan Rajasthan State Agriculture Marketing Board Operation and Maintenance Stage 7.38 26-Sep-2014 04-12-2019
2132 Cold Storage Project (Sikar) Government Infrastructure Projects (PPP) Social and Commercial Infrastructure Cold Chain Rajasthan Rajasthan State Agriculture Marketing Board Operation and Maintenance Stage 17.30 01-Apr-2010 13-09-2019
2133 Construction of multi chamber cold storage having capacity 4000 MT at Bhawani mandi Government Infrastructure Projects (PPP) Social and Commercial Infrastructure Cold Chain Rajasthan Rajasthan State Agriculture Marketing Board Operation and Maintenance Stage 7.37 13-Feb-2014 13-09-2019
2134 Construction of cold storage 6000 MT at KUMS Jodhpur Government Infrastructure Projects (PPP) Social and Commercial Infrastructure Cold Chain Rajasthan Rajasthan State Agriculture Marketing Board Operation and Maintenance Stage 5.11 15-Apr-2010 19-08-2019
2135 Operation & maintenance of multi chamber cold storages at Udaipur, Bhilwara & Pali districts. Government Infrastructure Projects (PPP) Social and Commercial Infrastructure Cold Chain Rajasthan Rajasthan State Agriculture Marketing Board Operation and Maintenance Stage 5.64 01-May-2013 19-08-2019
2136 Cold Storage Project (Alwar) Government Infrastructure Projects (PPP) Social and Commercial Infrastructure Cold Chain Rajasthan Rajasthan State Agriculture Marketing Board Operation and Maintenance Stage 17.30 22-Mar-2010 19-03-2018
2137 Solar Power Plant, Mainawali minor of Norangdeshar of Hanumangarh Region Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Rajasthan Rajasthan Renewable Energy Corporation Limited Operation and Maintenance Stage 26.00 29-Mar-2016 19-06-2019
2138 Solar power project in Rajasthan Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Rajasthan Renewable Energy Corporation Limited Completed 60.53 28-Mar-2013 10-06-2019
2139 Setting up of 1320 MW Suratgarh thermal power station at Suratgarh - Stage-V Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Rajasthan Rajasthan Rajya Vidyut Utpadan Nigam Limited Completed 6,192.37 28-May-2013 04-12-2019
2140 Thermal Power (Chhabra) Project - Unit 5 & 6 Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Rajasthan Rajasthan Rajya Vidyut Utpadan Nigam Limited Completed 7,920.00 28-Mar-2013 03-12-2019
2141 Combined Cycle Gas Based Power (Ramgarh) Project Stage IV*# Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Rajasthan Rajasthan Rajya Vidyut Utpadan Nigam Limited Under Construction 640.00 25-Apr-2012 27-11-2019
2142 Coal Based Power (Kalisindh) Project - Unit 1 & 2 Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Rajasthan Rajasthan Rajya Vidyut Utpadan Nigam Limited Completed 9,479.51 09-Jul-2008 13-10-2015
2143 Combined Cycle Gas Based Power (Ramgarh) Project Stage III Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Rajasthan Rajasthan Rajya Vidyut Utpadan Nigam Limited Completed 890.00 14-Jul-2009 13-10-2015
2144 Thermal Power (Chhabra) Project - Unit 3 & 4 Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Rajasthan Rajasthan Rajya Vidyut Utpadan Nigam Limited Completed 3,033.50 20-Aug-2008 13-10-2015
2145 Implementation of 400/220 kV Grid Substation at Chittorgarh Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Completed 50.45 25-Feb-2011 04-12-2019
2146 Implementation of 400/220 kV Pooling Substation at Ramgarh in Jaisalmer district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Completed 144.40 29-Oct-2014 04-12-2019
2147 Laying of 360.0 CKM Ramgarh-Bhadla transmission line Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Under Construction 114.03 16-Apr-2013 04-12-2019
2148 Laying of 480.0 CKM Akal-Jodhpur (New) transmission line Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Completed 310.52 17-Nov-2014 04-12-2019
2149 Transmission Line (Bhadla-Bikaner) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Under Construction 232.88 10-Apr-2013 04-12-2019
2150 Laying of 280.0 CKM Barmer-Bhinmal transmission line Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Completed 95.68 22-Jan-2016 03-12-2019
2151 Implementation of 400/220 kV Grid Substation at Babai * Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Under Construction 143.08 09-Aug-2009 26-11-2019
2152 Implementation of 400/220 kV Grid Substation at Jodhpur * Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Under Construction 100.38 27-Feb-2013 26-11-2019
2153 Laying of 200.0 CKM Ramgarh-Akal transmission line * Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Under Construction 74.05 27-Oct-2014 26-11-2019
2154 Laying of 213 CKM Phagi-Ajmer transmission line * Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Under Construction 84.00 02-Feb-2015 26-11-2019
2155 Laying of 320.4 CKM Bhilwara-Ajmer transmission line * Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Under Construction 55.63 26-Sep-2012 26-11-2019
2156 Laying of 480.0 CKM Suratgarh TPS-Babai transmission line * Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Under Construction 223.24 21-Jan-2011 26-11-2019
2157 Laying of 260.0 CKM Jaisalmer 2-Barmer transmission line* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Under Construction 96.32 25-May-2016 25-11-2019
2158 Setting up of 400/220 kV GSS at Jaisalmer-2* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Under Construction 121.34 16-Oct-2015 25-11-2019
2159 Substation (Bhadla) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Under Construction 151.50 03-Nov-2014 21-11-2019
2160 Development of 400 kV Babai (Jhunjhunu) - Jaipur (North) Double Circuit Twin Moose Power Transmission line * Government Infrastructure Projects (PPP) Energy Electricity transmission Rajasthan Rajasthan Rajya Vidyut Prasaran Nigam Limited Under Construction 294.00 Not Available 01-11-2019
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.