List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
1651 | Sardar Sarovar Project (Narmada) | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Under Construction | 39,240.45 | Not Available | 04-12-2019 |
1652 | Small Hydel Power (Kachchh Branch Canal) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Under Construction | 230.13 | 27-Aug-2014 | 04-12-2019 |
1653 | Solar Photovoltaic Power Plant (Vadodara Branch Canal - Chainage 12.43 km to 31.63 km) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Completed | 111.00 | 12-Mar-2015 | 04-12-2019 |
1654 | Small Hydel Power (Saurashtra Branch Canal) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Completed | 421.77 | 27-Aug-2014 | 03-12-2019 |
1655 | Solar Photovoltaic Power (Rawal) Project* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Under Construction | 253.77 | 31-Jan-2016 | 03-12-2019 |
1656 | Solar Photovoltaic Power (Vadodara Branch Canal - 5 MW) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Completed | 50.89 | 12-Mar-2015 | 03-12-2019 |
1657 | Small Hydel Power (Miyagam Branch Canal) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Under Construction | 149.46 | 07-Oct-2014 | 02-07-2019 |
1658 | Solar Photovoltaic Power Plant (Vadodara Branch Canal - chainage 25.60 kms to 36.80 kms) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Completed | 109.91 | 27-Jan-2014 | 02-07-2019 |
1659 | Saurashtra Branch Canal Pumping Station-1,2 & 3 (Phase-III & IV) Project | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Under Construction | 1,109.89 | 20-Jun-2015 | 22-07-2016 |
1660 | Saurashtra Branch Canal Pumping Station-4 & 5 (Phase-III & IV) Project | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Under Construction | 411.92 | 30-Jun-2015 | 22-07-2016 |
1661 | Small Hydel Power (Vadodara Branch Canal) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Under Construction | 88.28 | 12-Mar-2015 | 22-07-2016 |
1662 | 10 MW Solar Power (Vadodara) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Completed | 0.00 | Not Available | 27-09-2015 |
1663 | Coal Based Power (Kolam) Project* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Chhattisgarh | Sarda Energy and Minerals Limited | Under Construction | 1,225.00 | Not Available | 25-10-2019 |
1664 | Wind Power (Piploda and Namli) Project* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Saravanti Tuticorin Energy Generation Private Limited | Under Construction | 364.00 | 24-Jul-2013 | 21-11-2019 |
1665 | Biomass Power (Sathyamangalam) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Tamil Nadu | Saradha Papers and Boards Private Limited | Completed | 85.00 | Not Available | 27-09-2015 |
1666 | Belewadi Bagasse Power Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Maharashtra | Sar Senpati Santaji Ghorpade Sugar Factory Limited | Completed | 88.00 | Not Available | 27-09-2015 |
1667 | Setting up of 22 MW bagasse based power unit at Belewadi Kalmma in Kolhapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Maharashtra | Sar Senapati Santaji Ghorpade Sugar Factory Limited | Completed | 110.00 | 31-Jan-2012 | 09-11-2016 |
1668 | Setting up of 12 MW bagasse based power unit at Ghodasgaon in Jalgaon district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Maharashtra | Sant Muktai Sugar & Energy Limited | Under Construction | 60.00 | 25-Sep-2015 | 21-11-2019 |
1669 | Underground Drainage Scheme (Sangli & Miraj) - Phase II [Stage II]* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Maharashtra | Sangli Miraj Kupwad Municipal Corporation | Under Construction | 174.00 | 30-Apr-2013 | 27-11-2019 |
1670 | Setting up of 15 MW waste heat recovery based power unit at Sanghipuram in Kachchh district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Sanghi Industries Limited | Completed | 150.00 | 31-Jan-2016 | 03-06-2019 |
1671 | 25 MW Solar Power (Banaskantha) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Sandland Real Estate Private Limited | Completed | 250.00 | Not Available | 10-06-2019 |
1672 | Setting up of 50.4 MW wind power unit at Vidapanakallu in Anantapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Sandla Wind Project Private Limited | Completed | 376.80 | 12-Feb-2016 | 05-12-2016 |
1673 | Agro Park (Ferozpur)* | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Punjab | Sampurn Agri Ventures Private Limited | Under Construction | 400.00 | 30-Jan-2012 | 25-10-2019 |
1674 | Water Supply Scheme (Salem)* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Water supply pipeline | Tamil Nadu | Salem Municipal Corporation | Under Construction | 296.80 | 27-Aug-2010 | 27-11-2019 |
1675 | 65 MW Coal Based Power (Raigarh) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Chhattisgarh | Salasar Sponge and Power Limited | Completed | 280.00 | Not Available | 30-11-2015 |
1676 | Setting up a 20 MW solar photovoltaic power unit at Kalyandurg | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Saisudhir Energy Limited | Completed | 200.00 | 27-Nov-2012 | 11-06-2017 |
1677 | Wind Power (Petlawad - 81.9MW) Project* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Saimran Realities Limited | Under Construction | 573.30 | 16-Sep-2014 | 21-11-2019 |
1678 | Setting up of 10 MW Solar Power unit at Gurha in Bikaner district under JNNSM Phase I-Batch II | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Rajasthan | Sai Maithili Power Company Private Limited | Completed | 70.00 | 25-Jan-2012 | 31-10-2016 |
1679 | Implementation of sewerage scheme in Sagar * | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Madhya Pradesh | Sagar Municipal Corporation | Under Construction | 282.62 | 08-Jul-2016 | 25-11-2019 |
1680 | Waste Heat Recovery Power (Mattampally) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Telangana | Sagar Cements Limited | Under Construction | 65.23 | 05-May-2016 | 23-06-2016 |